Time and Work
- A certain number of persons can complete a piece of work in 55 days. If there were 6 persons more, the work could be finished in 11 days less. How many persons were originally there ?
-
View Hint View Answer Discuss in Forum
Originally, let there be x men
Now, more men, less days
(x + 6) : x : : 55 : 44So, x + 6 = 55 = 5 x 44 4
or 5x = 4x + 24
or x = 24
Aliter : Using Rule 23,
Here, D = 55. a = 6, d = 11
No of people initially= a(D - d) d = 6(55 - 11) = 24 11 Correct Option: B
Originally, let there be x men
Now, more men, less days
(x + 6) : x : : 55 : 44So, x + 6 = 55 = 5 x 44 4
or 5x = 4x + 24
or x = 24
Aliter : Using Rule 23,
Here, D = 55. a = 6, d = 11
No of people initially= a(D - d) d = 6(55 - 11) = 24 11
- A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in :
-
View Hint View Answer Discuss in Forum
Work done by (B + C) in 3 days.
= 3 × 1 + 1 9 12 = 1 + 1 = 4 + 3 = 7 3 4 12 12 Remaining work = 1 - 7 = 5 12 12
This part of work is done by A alone.Now, 1 part of work is done by A in 1 day 24 ∴ 5 part of work will be done by 12 A in = 24 × 5 = 10 days. 12 Correct Option: C
Work done by (B + C) in 3 days.
= 3 × 1 + 1 9 12 = 1 + 1 = 4 + 3 = 7 3 4 12 12 Remaining work = 1 - 7 = 5 12 12
This part of work is done by A alone.Now, 1 part of work is done by A in 1 day 24 ∴ 5 part of work will be done by 12 A in = 24 × 5 = 10 days. 12
- 8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?
-
View Hint View Answer Discuss in Forum
Using Rule 1,
Work done by 8 men in 6 days= 6 = 1 12 2 Remaining work = 1 - 1 = 1 2 2
4 more men are engaged.
∴ Total number of men
= 8 + 4 = 12
By work and time formulaW1 = W2 , we have M1D1 M2D2 1 = 1/2 8 × 12 12 × D2 ⇒ D2 = 1 × 8 × 12 = 4 days 2 12 Correct Option: C
Using Rule 1,
Work done by 8 men in 6 days= 6 = 1 12 2 Remaining work = 1 - 1 = 1 2 2
4 more men are engaged.
∴ Total number of men
= 8 + 4 = 12
By work and time formulaW1 = W2 , we have M1D1 M2D2 1 = 1/2 8 × 12 12 × D2 ⇒ D2 = 1 × 8 × 12 = 4 days 2 12
- A and B can together finish a work in 30 days. They worked together for 20 days and then B left. After another 20 days, A finished the remaining work. In how many days A alone can finish the job ?
-
View Hint View Answer Discuss in Forum
(A+B)’s 1 day’s work = 1 30 (A + B)’s 20 day’s work = 20 = 2 30 3 Remaining work = 1 - 2 = 1 3 3 Now 1 part of work is done by A in 20 days 3
∴ Whole work will be done by A alone in 20 × 3 = 60 days.Correct Option: B
(A+B)’s 1 day’s work = 1 30 (A + B)’s 20 day’s work = 20 = 2 30 3 Remaining work = 1 - 2 = 1 3 3 Now 1 part of work is done by A in 20 days 3
∴ Whole work will be done by A alone in 20 × 3 = 60 days.
- A and B can do a piece of work in 30 days while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work ?
-
View Hint View Answer Discuss in Forum
(A + B)’s day’s work = 1 30 (B + C)’s 1 day’s work = 1 24 (C + A)’s 1 day’s work = 1 20
∴ 2 (A + B + C)’s 1 day’s work= 1 + 1 + 1 30 24 20 = 4 + 5 + 6 = 15 = 1 120 120 8
∴ (A + B + C)’s 1 day’s work= 1 16
∴ (A + B + C)’s 10 days’ work= 10 = 5 16 8 ∴ Remaining work = 1 - 5 = 3 8 8
This part of work is done by A alone.Now A’s 1 day’s work = 1 - 1 16 24 = 3 - 2 = 1 48 48
∴ The required no. of days= 3 × 48 = 18 days 8 Correct Option: A
(A + B)’s day’s work = 1 30 (B + C)’s 1 day’s work = 1 24 (C + A)’s 1 day’s work = 1 20
∴ 2 (A + B + C)’s 1 day’s work= 1 + 1 + 1 30 24 20 = 4 + 5 + 6 = 15 = 1 120 120 8
∴ (A + B + C)’s 1 day’s work= 1 16
∴ (A + B + C)’s 10 days’ work= 10 = 5 16 8 ∴ Remaining work = 1 - 5 = 3 8 8
This part of work is done by A alone.Now A’s 1 day’s work = 1 - 1 16 24 = 3 - 2 = 1 48 48
∴ The required no. of days= 3 × 48 = 18 days 8