Time and Work


  1. A certain number of persons can complete a piece of work in 55 days. If there were 6 persons more, the work could be finished in 11 days less. How many persons were originally there ?









  1. View Hint View Answer Discuss in Forum

    Originally, let there be x men
    Now, more men, less days
    (x + 6) : x : : 55 : 44

    So,
    x + 6
    =
    55
    =
    5
    x444

    or 5x = 4x + 24
    or x = 24
    Aliter : Using Rule 23,
    Here, D = 55. a = 6, d = 11
    No of people initially
    =
    a(D - d)
    d

    =
    6(55 - 11)
    = 24
    11

    Correct Option: B

    Originally, let there be x men
    Now, more men, less days
    (x + 6) : x : : 55 : 44

    So,
    x + 6
    =
    55
    =
    5
    x444

    or 5x = 4x + 24
    or x = 24
    Aliter : Using Rule 23,
    Here, D = 55. a = 6, d = 11
    No of people initially
    =
    a(D - d)
    d

    =
    6(55 - 11)
    = 24
    11


  1. A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in :









  1. View Hint View Answer Discuss in Forum

    Work done by (B + C) in 3 days.

    = 3 ×
    1
    +
    1
    912

    =
    1
    +
    1
    =
    4 + 3
    =
    7
    341212

    Remaining work = 1 -
    7
    =
    5
    1212

    This part of work is done by A alone.
    Now,
    1
    part of work is done by A in 1 day
    24

    5
    part of work will be done by
    12

    A in = 24 ×
    5
    = 10 days.
    12

    Correct Option: C

    Work done by (B + C) in 3 days.

    = 3 ×
    1
    +
    1
    912

    =
    1
    +
    1
    =
    4 + 3
    =
    7
    341212

    Remaining work = 1 -
    7
    =
    5
    1212

    This part of work is done by A alone.
    Now,
    1
    part of work is done by A in 1 day
    24

    5
    part of work will be done by
    12

    A in = 24 ×
    5
    = 10 days.
    12



  1. 8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?









  1. View Hint View Answer Discuss in Forum

    Using Rule 1,
    Work done by 8 men in 6 days

    =
    6
    =
    1
    122

    Remaining work = 1 -
    1
    =
    1
    22

    4 more men are engaged.
    ∴ Total number of men
    = 8 + 4 = 12
    By work and time formula
    W1
    =
    W2
    , we have
    M1D1M2D2

    1
    =
    1/2
    8 × 1212 × D2

    ⇒ D2 =
    1
    ×
    8 × 12
    = 4 days
    212

    Correct Option: C

    Using Rule 1,
    Work done by 8 men in 6 days

    =
    6
    =
    1
    122

    Remaining work = 1 -
    1
    =
    1
    22

    4 more men are engaged.
    ∴ Total number of men
    = 8 + 4 = 12
    By work and time formula
    W1
    =
    W2
    , we have
    M1D1M2D2

    1
    =
    1/2
    8 × 1212 × D2

    ⇒ D2 =
    1
    ×
    8 × 12
    = 4 days
    212


  1. A and B can together finish a work in 30 days. They worked together for 20 days and then B left. After another 20 days, A finished the remaining work. In how many days A alone can finish the job ?









  1. View Hint View Answer Discuss in Forum

    (A+B)’s 1 day’s work =
    1
    30

    (A + B)’s 20 day’s work =
    20
    =
    2
    303

    Remaining work = 1 -
    2
    =
    1
    33

    Now
    1
    part of work is done by A in 20 days
    3

    ∴ Whole work will be done by A alone in 20 × 3 = 60 days.

    Correct Option: B

    (A+B)’s 1 day’s work =
    1
    30

    (A + B)’s 20 day’s work =
    20
    =
    2
    303

    Remaining work = 1 -
    2
    =
    1
    33

    Now
    1
    part of work is done by A in 20 days
    3

    ∴ Whole work will be done by A alone in 20 × 3 = 60 days.



  1. A and B can do a piece of work in 30 days while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work ?









  1. View Hint View Answer Discuss in Forum

    (A + B)’s day’s work =
    1
    30

    (B + C)’s 1 day’s work =
    1
    24

    (C + A)’s 1 day’s work =
    1
    20

    ∴ 2 (A + B + C)’s 1 day’s work
    =
    1
    +
    1
    +
    1
    302420

    =
    4 + 5 + 6
    =
    15
    =
    1
    1201208

    ∴ (A + B + C)’s 1 day’s work
    =
    1
    16

    ∴ (A + B + C)’s 10 days’ work
    =
    10
    =
    5
    168

    ∴ Remaining work = 1 -
    5
    =
    3
    88

    This part of work is done by A alone.
    Now A’s 1 day’s work =
    1
    -
    1
    1624

    =
    3 - 2
    =
    1
    4848

    ∴ The required no. of days
    =
    3
    × 48 = 18 days
    8

    Correct Option: A

    (A + B)’s day’s work =
    1
    30

    (B + C)’s 1 day’s work =
    1
    24

    (C + A)’s 1 day’s work =
    1
    20

    ∴ 2 (A + B + C)’s 1 day’s work
    =
    1
    +
    1
    +
    1
    302420

    =
    4 + 5 + 6
    =
    15
    =
    1
    1201208

    ∴ (A + B + C)’s 1 day’s work
    =
    1
    16

    ∴ (A + B + C)’s 10 days’ work
    =
    10
    =
    5
    168

    ∴ Remaining work = 1 -
    5
    =
    3
    88

    This part of work is done by A alone.
    Now A’s 1 day’s work =
    1
    -
    1
    1624

    =
    3 - 2
    =
    1
    4848

    ∴ The required no. of days
    =
    3
    × 48 = 18 days
    8