Time and Work


  1. A certain number of men complete a piece of work in 60 days. If there were 8 men more, the work could be finished in 10 days less. The number of men originally was









  1. View Hint View Answer Discuss in Forum

    Number of men originally = x (let)
    ∴ M1 D1 = M2 D2
    ⇒ x × 60 = (x + 8) × 50
    ⇒ 6x = 5x + 40
    ⇒ 6x – 5x = 40
    ⇒ x = 40 men
    Aliter : Using Rule 23,
    Here, D= 60, a = 8, d =10

    ∴ Required number=
    a(D - d)
    d

    =
    8(60 - 10)
    = 40
    10

    Correct Option: B

    Number of men originally = x (let)
    ∴ M1 D1 = M2 D2
    ⇒ x × 60 = (x + 8) × 50
    ⇒ 6x = 5x + 40
    ⇒ 6x – 5x = 40
    ⇒ x = 40 men
    Aliter : Using Rule 23,
    Here, D= 60, a = 8, d =10

    ∴ Required number=
    a(D - d)
    d

    =
    8(60 - 10)
    = 40
    10


  1. A, B and C together can do a piece of work in 40 days. After working with B and C for 16 days, A leaves and then B and C complete the remaining work in 40 days more. A alone could do the work in









  1. View Hint View Answer Discuss in Forum

    A, B and C together complete the work in 40 days.
    ∴ (A + B + C)’s 1 day’s work

    =
    1
    40

    ∴ (A + B + C)’s 16 days work
    =
    16
    =
    2
    405

    Remaining work = 1 –
    2
    =
    3
    55

    This part of work is done by B and C in 40 days.
    ∴ Time taken in doing
    3
    work = 40 days.
    5

    ∴ Time taken in doing in 1 work
    =
    40 × 5
    =
    200
    days
    33

    ∴ A’s day’s work = (A + B + C)’s 1 day’s work – (B + C)’s 1 day’s work
    =
    1
    -
    3
    40200

    =
    5 - 3
    =
    2
    =
    1
    200200100

    ∴ Required time = 100 days

    Correct Option: C

    A, B and C together complete the work in 40 days.
    ∴ (A + B + C)’s 1 day’s work

    =
    1
    40

    ∴ (A + B + C)’s 16 days work
    =
    16
    =
    2
    405

    Remaining work = 1 –
    2
    =
    3
    55

    This part of work is done by B and C in 40 days.
    ∴ Time taken in doing
    3
    work = 40 days.
    5

    ∴ Time taken in doing in 1 work
    =
    40 × 5
    =
    200
    days
    33

    ∴ A’s day’s work = (A + B + C)’s 1 day’s work – (B + C)’s 1 day’s work
    =
    1
    -
    3
    40200

    =
    5 - 3
    =
    2
    =
    1
    200200100

    ∴ Required time = 100 days



  1. If 12 men or 24 boys can do a work in 66 days, the number of days in which 15 men and 6 boys can do it is









  1. View Hint View Answer Discuss in Forum

    &because12 men ≡24 boys
    ∴ 1 man ≡2 boys
    ∴ 15 men + 6 boys
    = 30 boys + 6 boys = 36 boys
    ∴ M1D1 = M2D2
    ⇒ 24 × 66 = 36 × D2

    ⇒ D2 =
    24 × 66
    = 44 days
    36

    Aliter : Using Rule 12,
    Here, A = 12, B = 24
    a = 66, A1 = 15, B1 = 6
    ∴ Time taken =
    a ( A × B)
    A1B + B1A

    =
    66 ( 12 × 24)
    15 × 24 + 6 × 12

    =
    66 × 288
    360 + 72

    =
    66 × 288
    = 44 days.
    432

    Correct Option: A

    &because12 men ≡24 boys
    ∴ 1 man ≡2 boys
    ∴ 15 men + 6 boys
    = 30 boys + 6 boys = 36 boys
    ∴ M1D1 = M2D2
    ⇒ 24 × 66 = 36 × D2

    ⇒ D2 =
    24 × 66
    = 44 days
    36

    Aliter : Using Rule 12,
    Here, A = 12, B = 24
    a = 66, A1 = 15, B1 = 6
    ∴ Time taken =
    a ( A × B)
    A1B + B1A

    =
    66 ( 12 × 24)
    15 × 24 + 6 × 12

    =
    66 × 288
    360 + 72

    =
    66 × 288
    = 44 days.
    432


  1. 40 men can complete a work in 18 days. Eight days after they started working together, 10 more men joined them. How many days will they now take to complete the remaining work ?









  1. View Hint View Answer Discuss in Forum

    40 men complete the work in 18 days.

    ∴ Their 1 day’s work =
    1
    18

    ∴ Their 8 days’ work =
    8
    =
    4
    189

    Remaining work = 1 –
    4
    =
    5
    99

    New number of men = 40 + 10 = 50
    M1D1
    =
    M2D2
    W1W2

    40 × 18
    =
    50 × D2
    15/9

    ⇒ 40 × 18 = 90 × D2
    ⇒ D2 =
    40 × 18
    = 8 days.
    90

    Aliter : Using Rule 10,
    Here, A = 40, a = 18
    b = 8, B = 10
    Required Days =
    A(a - b)
    (A + B)

    =
    40(18 - 8)
    (40 + 10)

    =
    40 × 10
    = 8 days
    50

    Correct Option: B

    40 men complete the work in 18 days.

    ∴ Their 1 day’s work =
    1
    18

    ∴ Their 8 days’ work =
    8
    =
    4
    189

    Remaining work = 1 –
    4
    =
    5
    99

    New number of men = 40 + 10 = 50
    M1D1
    =
    M2D2
    W1W2

    40 × 18
    =
    50 × D2
    15/9

    ⇒ 40 × 18 = 90 × D2
    ⇒ D2 =
    40 × 18
    = 8 days.
    90

    Aliter : Using Rule 10,
    Here, A = 40, a = 18
    b = 8, B = 10
    Required Days =
    A(a - b)
    (A + B)

    =
    40(18 - 8)
    (40 + 10)

    =
    40 × 10
    = 8 days
    50



  1. 16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left and 4 women joined them. How many days will it take them to complete the remaining work ?









  1. View Hint View Answer Discuss in Forum

    Work done by 12 men in 8 days ≡ Work done by 16 women in 12 days.
    ⇒ 12 × 8 men ≡ 16 × 12 women
    ⇒ 1 man ≡ 2 women
    Now, work done by 12 men in 1 day

    =
    1
    8

    1 man’s 1 day’s work
    =
    1
    =
    1
    12 × 896

    ∴ 16 men’s 3 day’s work
    Remaining work = 1 –
    1
    =
    1
    22

    Now
    1
    work is done by 6 men and 4 women.
    2

    ∴ 6 men + 4 women
    = (6 + 2) men = 8 men
    M1D1
    =
    M2D2
    W1W2

    12 × 8
    =
    8 × D2
    11/2

    ⇒ D2 =
    12 × 8
    = 6 days.
    2 × 8

    Correct Option: B

    Work done by 12 men in 8 days ≡ Work done by 16 women in 12 days.
    ⇒ 12 × 8 men ≡ 16 × 12 women
    ⇒ 1 man ≡ 2 women
    Now, work done by 12 men in 1 day

    =
    1
    8

    1 man’s 1 day’s work
    =
    1
    =
    1
    12 × 896

    ∴ 16 men’s 3 day’s work
    Remaining work = 1 –
    1
    =
    1
    22

    Now
    1
    work is done by 6 men and 4 women.
    2

    ∴ 6 men + 4 women
    = (6 + 2) men = 8 men
    M1D1
    =
    M2D2
    W1W2

    12 × 8
    =
    8 × D2
    11/2

    ⇒ D2 =
    12 × 8
    = 6 days.
    2 × 8