Time and Work


  1. A and B together can complete a work in 12 days. A alone can complete in 20 days. If B does the work only half a day daily, then in how many days A and B together will complete the work ?









  1. View Hint View Answer Discuss in Forum

    B’s 1 day's work

    =
    1
    -
    1
    =
    5 - 3
    =
    1
    12206030

    ∴ B's
    1
    day's work =
    1
    260

    ∴ (A + B)'s 1 day's work
    =
    1
    +
    1
    =
    3 + 4
    =
    1
    20606015

    [ ∵ B works for half day daily]
    Hence, the work will be completed in 15 days.

    Correct Option: D

    B’s 1 day's work

    =
    1
    -
    1
    =
    5 - 3
    =
    1
    12206030

    ∴ B's
    1
    day's work =
    1
    260

    ∴ (A + B)'s 1 day's work
    =
    1
    +
    1
    =
    3 + 4
    =
    1
    20606015

    [ ∵ B works for half day daily]
    Hence, the work will be completed in 15 days.


  1. A and B working separately can do a piece of work in 9 and 12 days respectively. If they work for a day alternately with A beginning, the work would be completed in









  1. View Hint View Answer Discuss in Forum

    Part of work done by A and B in first two days

    =
    1
    +
    1
    =
    4 + 3
    =
    7
    9123636

    Part of work done in first 10 days = 35/36
    Remaining work = 1 -
    35
    =
    1
    3636

    Now it is the turn of A.
    ∴ Time taken by A
    =
    1
    × 9 =
    1
    days
    364

    += 10 1 4 10
    ∴ Total time = 10 +
    1
    = 10
    1
    days
    44

    Correct Option: C

    Part of work done by A and B in first two days

    =
    1
    +
    1
    =
    4 + 3
    =
    7
    9123636

    Part of work done in first 10 days = 35/36
    Remaining work = 1 -
    35
    =
    1
    3636

    Now it is the turn of A.
    ∴ Time taken by A
    =
    1
    × 9 =
    1
    days
    364

    += 10 1 4 10
    ∴ Total time = 10 +
    1
    = 10
    1
    days
    44



  1. A alone can complete a work in 18 days and B alone in 15 days. B alone worked at it for 10 days and then left the work. In how many more days, will A alone complete the remaining work ?









  1. View Hint View Answer Discuss in Forum

    Part of work done by B in 10 days

    = 10 ×
    1
    =
    2
    153

    Remaining work = 1 -
    2
    =
    1
    33

    ∴ Time taken by A =
    1
    × 18 = 6 days
    3

    Correct Option: C

    Part of work done by B in 10 days

    = 10 ×
    1
    =
    2
    153

    Remaining work = 1 -
    2
    =
    1
    33

    ∴ Time taken by A =
    1
    × 18 = 6 days
    3


  1. A can complete a piece of work in 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is









  1. View Hint View Answer Discuss in Forum

    (B + C)’s 2 days’ work

    = 2
    1
    +
    1
    = 2
    3 + 2
    302060

    =
    1
    part
    6

    Remaining work = 1 -
    1
    =
    5
    part
    66

    ∴ Time taken by A to complete this part of work
    =
    5
    × 18 = 15 days
    6

    Correct Option: C

    (B + C)’s 2 days’ work

    = 2
    1
    +
    1
    = 2
    3 + 2
    302060

    =
    1
    part
    6

    Remaining work = 1 -
    1
    =
    5
    part
    66

    ∴ Time taken by A to complete this part of work
    =
    5
    × 18 = 15 days
    6



  1. A and B alone can complete work in 9 days and18 days respectively. They worked together; however 3 days before the completion of the work A left. In how many days was the work completed ?









  1. View Hint View Answer Discuss in Forum

    Let the work be completed in x days.
    According to the question,
    A worked for (x –3) days, while B worked for x days.

    x - 3
    +
    x
    = 1
    918

    2x - 6 + x
    = 1 ⇒ 3x - 6 = 18
    18

    ⇒ 3x = 18 + 6 = 24
    ∵ x =
    24
    = 8 days
    3

    Aliter :
    Using Rule 8,
    Here, x = 9, y = 18, m = 3
    Total time taken =
    (x + m)y
    x + y

    =
    (9 + 3) × 18
    9 + 18

    =
    12 × 18
    = 8 days
    27

    Correct Option: B

    Let the work be completed in x days.
    According to the question,
    A worked for (x –3) days, while B worked for x days.

    x - 3
    +
    x
    = 1
    918

    2x - 6 + x
    = 1 ⇒ 3x - 6 = 18
    18

    ⇒ 3x = 18 + 6 = 24
    ∵ x =
    24
    = 8 days
    3

    Aliter :
    Using Rule 8,
    Here, x = 9, y = 18, m = 3
    Total time taken =
    (x + m)y
    x + y

    =
    (9 + 3) × 18
    9 + 18

    =
    12 × 18
    = 8 days
    27