Time and Work
- A alone can do a piece of work in 20 days and B alone in 30 days. They begin to work together. They will finish half of the work in :
-
View Hint View Answer Discuss in Forum
(A+B)’s 1 day’s work
= 1 + 1 = 3 + 2 = 1 20 30 60 12
∴ Work done in 6 days= 6 = 1 12 2
Aliter : Using basics of Rule 2,
Here, x = 20, y = 30
They do the work in= xy days x + y = 20 × 30 = 12 days 20 + 30
Half of the work they do in 6 daysCorrect Option: D
(A+B)’s 1 day’s work
= 1 + 1 = 3 + 2 = 1 20 30 60 12
∴ Work done in 6 days= 6 = 1 12 2
Aliter : Using basics of Rule 2,
Here, x = 20, y = 30
They do the work in= xy days x + y = 20 × 30 = 12 days 20 + 30
Half of the work they do in 6 days
- A can do a work in 20 days and B in 40 days. If they work on it together for 5 days, then the fraction of the work that is left is :
-
View Hint View Answer Discuss in Forum
Using basics of Rule 2,
(A + B)’s 5 days’ work= 5 1 + 1 20 40 = 5 2 + 1 40 = 15 = 3 40 8 ∴ Remaining work = 1 - 3 = 5 8 8 Correct Option: A
Using basics of Rule 2,
(A + B)’s 5 days’ work= 5 1 + 1 20 40 = 5 2 + 1 40 = 15 = 3 40 8 ∴ Remaining work = 1 - 3 = 5 8 8
- A is twice as good a workman as B and together they finish a piece of work in 14 days. The number of days taken by A alone to finish the work is
-
View Hint View Answer Discuss in Forum
Using Rule 2,
If A completes the work in x days, B will take 2x days.∴ 1 + 1 = 1 x 2x 14 = 2 + 1 = 1 2x 14
⇒ 2x = 42 ⇒ x = 21 days
Correct Option: B
Using Rule 2,
If A completes the work in x days, B will take 2x days.∴ 1 + 1 = 1 x 2x 14 = 2 + 1 = 1 2x 14
⇒ 2x = 42 ⇒ x = 21 days
- Sunil completes a work in 4 days, whereas Dinesh completes the work in 6 days. Ramesh works
times as fast as Sunil. The three together can complete the work in1 1 2
-
View Hint View Answer Discuss in Forum
Using Rule 3,
Time taken by Ramesh= 4 × 2 = 8 days 3 3
Work done by all three in 1 day1 + 1 + 3 4 6 8
∴ Required time= 24 = 1 5 days 19 19 Correct Option: D
Using Rule 3,
Time taken by Ramesh= 4 × 2 = 8 days 3 3
Work done by all three in 1 day1 + 1 + 3 4 6 8
∴ Required time= 24 = 1 5 days 19 19
- Two workers A and B working together completed a job in 5 days. If A worked twice as efficiently as he actually did and B worked 1/3 as efficiently as he actually did, the work would have been completed in 3 days. To complete the job alone, A would require
-
View Hint View Answer Discuss in Forum
Using Rule 2,
If A alone does the work in x days and B alone does the work in y days, then1 + 1 = 1 ...........(i) x y 5 Again, 2 + 1 = 1 ...........(ii) x 3y 3
By equation (ii) × 3 – (i),⇒ 6 + 1 - 1 - 1 = 1 - 1 x y x y 5 6 - 1 = 4 x x 5 = 6 - 1 = 4 x 5 ⇒ x = 25 = 6 1 days 4 4 Correct Option: B
Using Rule 2,
If A alone does the work in x days and B alone does the work in y days, then1 + 1 = 1 ...........(i) x y 5 Again, 2 + 1 = 1 ...........(ii) x 3y 3
By equation (ii) × 3 – (i),⇒ 6 + 1 - 1 - 1 = 1 - 1 x y x y 5 6 - 1 = 4 x x 5 = 6 - 1 = 4 x 5 ⇒ x = 25 = 6 1 days 4 4