Time and Work
- A contractor undertook to complete a project in 90 days and employed 60 men on it. After 60 days, he found that 3/4 of the work has already been completed. How many men can he discharge so that the project may be completed exactly on time ?
-
View Hint View Answer Discuss in Forum
Using basics of Rule 1,
⇒ 30 × 3 × x = 60 × 1 × 60 4 4 ⇒ x = 60 × 60 = 40 30 × 3
∴ 20 men should be discharged.Correct Option: B
Using basics of Rule 1,
⇒ 30 × 3 × x = 60 × 1 × 60 4 4 ⇒ x = 60 × 60 = 40 30 × 3
∴ 20 men should be discharged.
- A can complete 2/3 of a work in 4 days and B can complete 3/5 of the work in 6 days. In how many days can both A and B together complete the work ?
-
View Hint View Answer Discuss in Forum
Using basics of Rule 2,
Time taken by A to complete the work= 4 × 3 = 6 days 2
Time taken by B to complete the work= 6 × 5 = 10 days 3
∴ (A + B)’s 1 day’s work= 1 + 1 = 5 + 3 = 4 6 10 30 15
∴ A and B together will complete the work in15 = 3 3 days. 4 4 Correct Option: C
Using basics of Rule 2,
Time taken by A to complete the work= 4 × 3 = 6 days 2
Time taken by B to complete the work= 6 × 5 = 10 days 3
∴ (A + B)’s 1 day’s work= 1 + 1 = 5 + 3 = 4 6 10 30 15
∴ A and B together will complete the work in15 = 3 3 days. 4 4
- A can complete 1/3 of a work in 5 days and B, 2/5 of the work in 10 days. In how many days both A and B together can complete the work ?
-
View Hint View Answer Discuss in Forum
Using basics of Rule 2,
Time taken by A alone in doing the work = 15 days
Time taken by B alone in doing the work= 10 × 5 = 25 days 2
∴ (A + B)’s 1 day’s work= 1 + 1 = 5 + 3 = 8 15 25 75 75
∴ Hence, the work will be completed in75 = 9 3 days. 8 8 Correct Option: B
Using basics of Rule 2,
Time taken by A alone in doing the work = 15 days
Time taken by B alone in doing the work= 10 × 5 = 25 days 2
∴ (A + B)’s 1 day’s work= 1 + 1 = 5 + 3 = 8 15 25 75 75
∴ Hence, the work will be completed in75 = 9 3 days. 8 8
- If 28 men complete 7/8 of a piece of work in a week, then the number of men, who must be engaged to get the remaining work completed in another week, is
-
View Hint View Answer Discuss in Forum
Using basics of Rule 1,
= 7 : 1 :: 28 : x 8 8
where x is no. of men⇒ 7 × x 1 × 28 8 8 ⇒ x = 28 × 8 = 4 7 × 8 Correct Option: C
Using basics of Rule 1,
= 7 : 1 :: 28 : x 8 8
where x is no. of men⇒ 7 × x 1 × 28 8 8 ⇒ x = 28 × 8 = 4 7 × 8
- A can do 1/2 of a piece of work in 5 days, B can do 3/5 of the same work in 9 days and C can do 2/3 of that work in 8 days. In how many days can three of them together do the work ?
-
View Hint View Answer Discuss in Forum
Using basics of Rule 3,
A can do 1 work in 5 days. 2
∴ A can do 1 work in 10 days
Similarly,B can do 1 work in 5 × 9 = 15 days 3 C can do 1 work in 8 × 3 = 12 days. 2
Now,A’s 1 day’s work = 1 10 B’s 1 day’s work = 1 15 C’s 1 day’s work = 1 12
∴ (A + B + C)’s 1 day’s work= 1 + 1 + 1 10 15 12 = 6 + 4 + 5 = 15 = 1 60 60 4
Hence, (A + B + C) together can complete the work in 4 days.Correct Option: D
Using basics of Rule 3,
A can do 1 work in 5 days. 2
∴ A can do 1 work in 10 days
Similarly,B can do 1 work in 5 × 9 = 15 days 3 C can do 1 work in 8 × 3 = 12 days. 2
Now,A’s 1 day’s work = 1 10 B’s 1 day’s work = 1 15 C’s 1 day’s work = 1 12
∴ (A + B + C)’s 1 day’s work= 1 + 1 + 1 10 15 12 = 6 + 4 + 5 = 15 = 1 60 60 4
Hence, (A + B + C) together can complete the work in 4 days.