Time and Work


  1. A contractor undertook to complete a project in 90 days and employed 60 men on it. After 60 days, he found that 3/4 of the work has already been completed. How many men can he discharge so that the project may be completed exactly on time ?









  1. View Hint View Answer Discuss in Forum

    Using basics of Rule 1,

    ⇒ 30 ×
    3
    × x = 60 ×
    1
    × 60
    44

    ⇒ x =
    60 × 60
    = 40
    30 × 3

    ∴ 20 men should be discharged.

    Correct Option: B

    Using basics of Rule 1,

    ⇒ 30 ×
    3
    × x = 60 ×
    1
    × 60
    44

    ⇒ x =
    60 × 60
    = 40
    30 × 3

    ∴ 20 men should be discharged.


  1. A can complete 2/3 of a work in 4 days and B can complete 3/5 of the work in 6 days. In how many days can both A and B together complete the work ?









  1. View Hint View Answer Discuss in Forum

    Using basics of Rule 2,
    Time taken by A to complete the work

    =
    4 × 3
    = 6 days
    2

    Time taken by B to complete the work
    =
    6 × 5
    = 10 days
    3

    ∴ (A + B)’s 1 day’s work
    =
    1
    +
    1
    =
    5 + 3
    =
    4
    6103015

    ∴ A and B together will complete the work in
    15
    = 3
    3
    days.
    44

    Correct Option: C

    Using basics of Rule 2,
    Time taken by A to complete the work

    =
    4 × 3
    = 6 days
    2

    Time taken by B to complete the work
    =
    6 × 5
    = 10 days
    3

    ∴ (A + B)’s 1 day’s work
    =
    1
    +
    1
    =
    5 + 3
    =
    4
    6103015

    ∴ A and B together will complete the work in
    15
    = 3
    3
    days.
    44



  1. A can complete 1/3 of a work in 5 days and B, 2/5 of the work in 10 days. In how many days both A and B together can complete the work ?









  1. View Hint View Answer Discuss in Forum

    Using basics of Rule 2,
    Time taken by A alone in doing the work = 15 days
    Time taken by B alone in doing the work

    =
    10 × 5
    = 25 days
    2

    ∴ (A + B)’s 1 day’s work
    =
    1
    +
    1
    =
    5 + 3
    =
    8
    15257575

    ∴ Hence, the work will be completed in
    75
    = 9
    3
    days.
    88

    Correct Option: B

    Using basics of Rule 2,
    Time taken by A alone in doing the work = 15 days
    Time taken by B alone in doing the work

    =
    10 × 5
    = 25 days
    2

    ∴ (A + B)’s 1 day’s work
    =
    1
    +
    1
    =
    5 + 3
    =
    8
    15257575

    ∴ Hence, the work will be completed in
    75
    = 9
    3
    days.
    88


  1. If 28 men complete 7/8 of a piece of work in a week, then the number of men, who must be engaged to get the remaining work completed in another week, is









  1. View Hint View Answer Discuss in Forum

    Using basics of Rule 1,

    =
    7
    :
    1
    :: 28 : x
    88

    where x is no. of men
    7
    × x
    1
    × 28
    88

    ⇒ x =
    28 × 8
    = 4
    7 × 8

    Correct Option: C

    Using basics of Rule 1,

    =
    7
    :
    1
    :: 28 : x
    88

    where x is no. of men
    7
    × x
    1
    × 28
    88

    ⇒ x =
    28 × 8
    = 4
    7 × 8



  1. A can do 1/2 of a piece of work in 5 days, B can do 3/5 of the same work in 9 days and C can do 2/3 of that work in 8 days. In how many days can three of them together do the work ?









  1. View Hint View Answer Discuss in Forum

    Using basics of Rule 3,

    A can do
    1
    work in 5 days.
    2

    ∴ A can do 1 work in 10 days
    Similarly,
    B can do 1 work in
    5
    × 9 = 15 days
    3

    C can do 1 work in 8 ×
    3
    = 12 days.
    2

    Now,
    A’s 1 day’s work =
    1
    10

    B’s 1 day’s work =
    1
    15

    C’s 1 day’s work =
    1
    12

    ∴ (A + B + C)’s 1 day’s work
    =
    1
    +
    1
    +
    1
    101512

    =
    6 + 4 + 5
    =
    15
    =
    1
    60604

    Hence, (A + B + C) together can complete the work in 4 days.

    Correct Option: D

    Using basics of Rule 3,

    A can do
    1
    work in 5 days.
    2

    ∴ A can do 1 work in 10 days
    Similarly,
    B can do 1 work in
    5
    × 9 = 15 days
    3

    C can do 1 work in 8 ×
    3
    = 12 days.
    2

    Now,
    A’s 1 day’s work =
    1
    10

    B’s 1 day’s work =
    1
    15

    C’s 1 day’s work =
    1
    12

    ∴ (A + B + C)’s 1 day’s work
    =
    1
    +
    1
    +
    1
    101512

    =
    6 + 4 + 5
    =
    15
    =
    1
    60604

    Hence, (A + B + C) together can complete the work in 4 days.