Time and Work


  1. Two men can do a piece of work in x days. But y women can do that in 3 days. Then the ratio of the work done by 1 man and 1 woman is









  1. View Hint View Answer Discuss in Forum

    1 man’s 1 day’s work =
    1
    2x

    1 woman’s 1 day’s work =
    1
    3y

    ∴ Required ratio
    =
    1
    :
    1
    = 3y : 2x
    2x3y

    Correct Option: A

    1 man’s 1 day’s work =
    1
    2x

    1 woman’s 1 day’s work =
    1
    3y

    ∴ Required ratio
    =
    1
    :
    1
    = 3y : 2x
    2x3y


  1. A man and a woman working together can do a certain work in 18 days. Their skills in doing the work are in the ratio 3 : 2.
    How many days will the woman take to finish the work alone?









  1. View Hint View Answer Discuss in Forum

    Man : Woman (efficiency)
    i.e., Woman completes 2/5 th work in 18 days.
    ∴ Time taken by the woman to complete the whole work

    =
    18 × 5
    = 45 days
    2

    Correct Option: A

    Man : Woman (efficiency)
    i.e., Woman completes 2/5 th work in 18 days.
    ∴ Time taken by the woman to complete the whole work

    =
    18 × 5
    = 45 days
    2



  1. Twenty women together can complete a work in 16 days. 16 men together can complete the same work in 15 days. The ratio of the working capacity of a man to that of a woman is :









  1. View Hint View Answer Discuss in Forum

    20 × 16 women ≡ 16 × 15 men
    ⇒ 4 women ≡ 3 men

    men
    =
    4
    women3

    Hence, working capacity of man : woman = 4 : 3

    Correct Option: B

    20 × 16 women ≡ 16 × 15 men
    ⇒ 4 women ≡ 3 men

    men
    =
    4
    women3

    Hence, working capacity of man : woman = 4 : 3


  1. A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?









  1. View Hint View Answer Discuss in Forum

    Scheduled time to complete the work = 40 days

    25 men in 24 days do
    1
    work
    3

    ∴ 1 man in 1 day does
    1
    =
    1
    work.
    3 × 25 × 241800

    Work remaining
    = 1 -
    1
    =
    2
    33

    The work is to be completed 4 days before schedule i.e., in (40 – 4) 36 days
    No. of days left for
    2
    rd work
    3

    = 36 – 24 = 12 days
    1
    1800

    work is done in 1 day by 1 man.
    2
    work will be done in 12 days by
    3

    1800 ×
    2
    ×
    1
    = 100 men
    312

    25 men are already working
    ∴ Extra men to be employed
    = 100 – 25 = 75

    Correct Option: C

    Scheduled time to complete the work = 40 days

    25 men in 24 days do
    1
    work
    3

    ∴ 1 man in 1 day does
    1
    =
    1
    work.
    3 × 25 × 241800

    Work remaining
    = 1 -
    1
    =
    2
    33

    The work is to be completed 4 days before schedule i.e., in (40 – 4) 36 days
    No. of days left for
    2
    rd work
    3

    = 36 – 24 = 12 days
    1
    1800

    work is done in 1 day by 1 man.
    2
    work will be done in 12 days by
    3

    1800 ×
    2
    ×
    1
    = 100 men
    312

    25 men are already working
    ∴ Extra men to be employed
    = 100 – 25 = 75



  1. Working efficiencies of P and Q for completing a piece of work are in the ratio 3 : 4. The number of days to be taken by them to complete the work will be in the ratio









  1. View Hint View Answer Discuss in Forum

    Using Rule 15,
    Efficiency and time taken are inversely proportional.
    ∴ Required ratio = 4 : 3

    Correct Option: D

    Using Rule 15,
    Efficiency and time taken are inversely proportional.
    ∴ Required ratio = 4 : 3