Time and Work


  1. A father can do a job as fast as his two sons working together. If one son does the job in 3 hours and the other in 6 hours, the number of hours taken by the father, to do the job alone is









  1. View Hint View Answer Discuss in Forum

    Work done by two sons in an hour

    =
    1
    +
    1
    =
    1
    362

    ∴ Work done by father in an hour
    =
    1
    2

    ∴ Required time = 2 hours

    Correct Option: B

    Work done by two sons in an hour

    =
    1
    +
    1
    =
    1
    362

    ∴ Work done by father in an hour
    =
    1
    2

    ∴ Required time = 2 hours


  1. If 42 persons consume 144 kg of wheat in 15 days, then in how many days will 30 persons consume 45 kg of wheat ?









  1. View Hint View Answer Discuss in Forum


    30 : 42
    : : 15 : x
    144 : 48

    ⇒ 30 × 144 × x = 42 × 48 × 15
    ⇒ x =
    42 × 48 × 15
    = 7 days
    30 × 144

    Correct Option: B


    30 : 42
    : : 15 : x
    144 : 48

    ⇒ 30 × 144 × x = 42 × 48 × 15
    ⇒ x =
    42 × 48 × 15
    = 7 days
    30 × 144



  1. A can do as much work in 4 days as B can do in 5 days, and B can do as much work in 6 days as C in 7 days. In what time will C do a piece of work which A can do in a week ?









  1. View Hint View Answer Discuss in Forum

    A’s 4 days’ work = B’s 5 days’ work
    ⇒ A : B = 4 : 5
    Again, B : C = 6 : 7
    ∴ A : B : C = 4 × 6 : 5 × 6 : 5 × 7 = 24 : 30 : 35
    ∵ Time taken by A = 7 days

    ∴ Time taken by C =
    35
    × 7
    24

    =
    245
    = 10
    5
    days
    2424

    Correct Option: A

    A’s 4 days’ work = B’s 5 days’ work
    ⇒ A : B = 4 : 5
    Again, B : C = 6 : 7
    ∴ A : B : C = 4 × 6 : 5 × 6 : 5 × 7 = 24 : 30 : 35
    ∵ Time taken by A = 7 days

    ∴ Time taken by C =
    35
    × 7
    24

    =
    245
    = 10
    5
    days
    2424


  1. A and B can do a piece of work in 18 days, B and C in 24 days, A and C in 36 days. Working together they can do the work in









  1. View Hint View Answer Discuss in Forum

    (A + B)’s 1 day’s work =
    1
    18

    (B + C)’s 1 day’s work =
    1
    24

    (C + A)’s 1 day’s work =
    1
    36

    On adding all three,
    2 (A + B + C)’s 1 day’s work
    =
    1
    +
    1
    +
    1
    =
    3 + 4 + 2
    18243672

    =
    9
    =
    1
    728

    ∴ (A + B + C)’s 1 day’s work
    =
    1
    16

    ∴ Required time = 16 days

    Correct Option: C

    (A + B)’s 1 day’s work =
    1
    18

    (B + C)’s 1 day’s work =
    1
    24

    (C + A)’s 1 day’s work =
    1
    36

    On adding all three,
    2 (A + B + C)’s 1 day’s work
    =
    1
    +
    1
    +
    1
    =
    3 + 4 + 2
    18243672

    =
    9
    =
    1
    728

    ∴ (A + B + C)’s 1 day’s work
    =
    1
    16

    ∴ Required time = 16 days



  1. A canal of a village can be cleaned by 24 villagers in 12 days. The number of days in which 36 villagers can clean the canal is









  1. View Hint View Answer Discuss in Forum

    M1D1 = M2D2
    ⇒ 24 × 12 = 36 × D2

    ⇒ D2 =
    24 × 12
    = 8 days
    36

    Correct Option: B

    M1D1 = M2D2
    ⇒ 24 × 12 = 36 × D2

    ⇒ D2 =
    24 × 12
    = 8 days
    36