Time and Work


  1. A and B can complete a piece of work in 45 and 40 days respectively. Both started to work together, but after some days A left and B alone completed the rest work in 23 days. For how many days did A work?









  1. View Hint View Answer Discuss in Forum

    Using Rule 2,
    Let A worked for x days.

    A’s 1 day’s work =
    1
    45

    ∴ A’s x day’s work=
    x
    45

    B’s 1 day’s work =
    1
    40

    ∴ B’s x day’s work
    =
    1
    × x =
    x
    4040

    (A + B) together worked for x days.
    ∴ (A + B)’s x day’s work
    =
    x
    +
    x
    4540

    =
    8x + 9x
    =
    17x
    360360

    ∴ Remaining work
    = 1 -
    17x
    =
    360 - 17x
    360360

    This part of work, i.e.,
    360 - 17x
    360

    is completed by B alone in 23 days.
    360 - 17x
    = 23 × B’s 1 day’s work
    360

    360 - 17x
    360

    = 23 ×
    1
    =
    23
    4040

    ∴ 360 – 17x
    =
    23
    × 360 = 207
    40

    ∴ 17x = 360 – 207 = 153
    ⇒ x =
    153
    = 9 days
    17

    Hence, A worked for 9 days.

    Correct Option: D

    Using Rule 2,
    Let A worked for x days.

    A’s 1 day’s work =
    1
    45

    ∴ A’s x day’s work=
    x
    45

    B’s 1 day’s work =
    1
    40

    ∴ B’s x day’s work
    =
    1
    × x =
    x
    4040

    (A + B) together worked for x days.
    ∴ (A + B)’s x day’s work
    =
    x
    +
    x
    4540

    =
    8x + 9x
    =
    17x
    360360

    ∴ Remaining work
    = 1 -
    17x
    =
    360 - 17x
    360360

    This part of work, i.e.,
    360 - 17x
    360

    is completed by B alone in 23 days.
    360 - 17x
    = 23 × B’s 1 day’s work
    360

    360 - 17x
    360

    = 23 ×
    1
    =
    23
    4040

    ∴ 360 – 17x
    =
    23
    × 360 = 207
    40

    ∴ 17x = 360 – 207 = 153
    ⇒ x =
    153
    = 9 days
    17

    Hence, A worked for 9 days.


  1. Ram can do a piece of work in 20 days and Shyam in 30 days. They work together for 10 days. After that Shyam leaves and rest of the work is completed by Ram alone. How long does it take Ram to finish the remaining work?









  1. View Hint View Answer Discuss in Forum

    Ram’s 1 day’s work =
    1
    20

    Shyam’s 1 day’s work =
    1
    30

    ∴ (Ram + Shyam)’s 1 day’s work
    =
    1
    +
    1
    =
    3 + 2
    203060

    =
    5
    =
    1
    6012

    ∴ (Ram + Shyam)’s 10 days’ work
    = 10 ×
    1
    =
    5
    126

    ⇒ Remaining work
    = 1 -
    5
    =
    1
    66

    Now, 1/6 work is completed by Ram alone.
    To finish this part Ram will take

    ==
    1
    Remaining work
    6
    Ram’s1 day’s work
    1
    20

    =
    1
    × 20 =
    10
    = 3
    1
    days.
    633

    Correct Option: C

    Ram’s 1 day’s work =
    1
    20

    Shyam’s 1 day’s work =
    1
    30

    ∴ (Ram + Shyam)’s 1 day’s work
    =
    1
    +
    1
    =
    3 + 2
    203060

    =
    5
    =
    1
    6012

    ∴ (Ram + Shyam)’s 10 days’ work
    = 10 ×
    1
    =
    5
    126

    ⇒ Remaining work
    = 1 -
    5
    =
    1
    66

    Now, 1/6 work is completed by Ram alone.
    To finish this part Ram will take

    ==
    1
    Remaining work
    6
    Ram’s1 day’s work
    1
    20

    =
    1
    × 20 =
    10
    = 3
    1
    days.
    633



  1. A can do a piece of work in 40 days. He works on it for 5 days and then B completes it in 21 days. How long will A and B together take to complete the work?









  1. View Hint View Answer Discuss in Forum

    Using Rule 2,

    A’s 1 day’s work =
    1
    40

    ∴ A’s 5 days’ work
    =
    5
    =
    1
    408

    Remaining work
    = 1 -
    1
    =
    7
    88

    This part of work is done by B in 21 days.
    ∴ B’s 1 day’s work
    =
    7
    =
    1
    8 × 2124

    ∴ (A + B)’s 1 day’s work
    =
    1
    +
    1
    =
    3 + 5
    4024120

    =
    8
    =
    1
    12015

    Hence, A and B together will
    complete the work in 15 days.

    Correct Option: B

    Using Rule 2,

    A’s 1 day’s work =
    1
    40

    ∴ A’s 5 days’ work
    =
    5
    =
    1
    408

    Remaining work
    = 1 -
    1
    =
    7
    88

    This part of work is done by B in 21 days.
    ∴ B’s 1 day’s work
    =
    7
    =
    1
    8 × 2124

    ∴ (A + B)’s 1 day’s work
    =
    1
    +
    1
    =
    3 + 5
    4024120

    =
    8
    =
    1
    12015

    Hence, A and B together will
    complete the work in 15 days.


  1. A, B and C can complete a work in 8 days. B alone can do it in 18 days and C alone can do it in 24 days. In how many days can A alone do the same work?









  1. View Hint View Answer Discuss in Forum

    (A + B + C)’s 1 day’s work

    =
    1
    8

    B’s 1 day’s work =
    1
    18

    C’s 1 day’s work =
    1
    24

    ∴ A’s 1 day’s work
    = (A + B + C)’s 1 day’s work – B’s
    1 day’s work – C’s 1 day’s work
    =
    1
    -
    1
    -
    1
    81824

    =
    9 - 4 - 3
    =
    2
    =
    1
    727236

    ⇒ A’s 1 day’s work =
    1
    36

    ∴ A alone can do the same work in 36 days.
    Aliter : Using Rule 18,
    Here, x = 8, y = 18, z = 24
    Required time
    =
    xyz
    zy - x(y + z)

    =
    8 × 18 × 24
    24 × 18 - 8(18 + 24)

    =
    8 × 18 × 24
    432 - 336

    =
    8 × 18 × 24
    = 36 days
    96

    Correct Option: A

    (A + B + C)’s 1 day’s work

    =
    1
    8

    B’s 1 day’s work =
    1
    18

    C’s 1 day’s work =
    1
    24

    ∴ A’s 1 day’s work
    = (A + B + C)’s 1 day’s work – B’s
    1 day’s work – C’s 1 day’s work
    =
    1
    -
    1
    -
    1
    81824

    =
    9 - 4 - 3
    =
    2
    =
    1
    727236

    ⇒ A’s 1 day’s work =
    1
    36

    ∴ A alone can do the same work in 36 days.
    Aliter : Using Rule 18,
    Here, x = 8, y = 18, z = 24
    Required time
    =
    xyz
    zy - x(y + z)

    =
    8 × 18 × 24
    24 × 18 - 8(18 + 24)

    =
    8 × 18 × 24
    432 - 336

    =
    8 × 18 × 24
    = 36 days
    96



  1. A and B can do a piece of work in 12 days, B and C in 15 days; C and A in 20 days. In how many days will they finish it working together? In what time can A do it separately?









  1. View Hint View Answer Discuss in Forum

    (A + B)’s 1 day’s work

    =
    1
    12

    (B + C)’s 1 day’s work
    =
    1
    15

    (C + A)’s 1 day’s work
    =
    1
    20

    Adding all,
    2 (A + B + C)’s 1 day’s work
    =
    1
    +
    1
    +
    1
    121520

    =
    5 + 4 + 3
    =
    12
    =
    1
    60605

    ∴ (A + B + C)’s 1 day’s work
    =
    1
    =
    1
    5 × 210

    ∴ (A + B + C) together can complete the work in 10 days.
    Now, A’s 1 day’s work
    = (A + B + C)’s 1 day’s work –
    (B + C)’s 1 day’s work
    =
    1
    -
    1
    =
    3 - 2
    =
    1
    10153030

    ∴ A alone can finish the work in 30 days.
    Aliter : Using Rule 19,
    Here, x = 12, y = 15, z = 20
    A alone can do in
    =
    2xyz
    xy + yz - zx

    =
    2 × 12 × 15 × 20
    12 × 15 + 15 × 20 - 20 × 12

    =
    24 × 300
    180 + 300 - 240

    =
    24 × 300
    = 30 days
    240

    Correct Option: D

    (A + B)’s 1 day’s work

    =
    1
    12

    (B + C)’s 1 day’s work
    =
    1
    15

    (C + A)’s 1 day’s work
    =
    1
    20

    Adding all,
    2 (A + B + C)’s 1 day’s work
    =
    1
    +
    1
    +
    1
    121520

    =
    5 + 4 + 3
    =
    12
    =
    1
    60605

    ∴ (A + B + C)’s 1 day’s work
    =
    1
    =
    1
    5 × 210

    ∴ (A + B + C) together can complete the work in 10 days.
    Now, A’s 1 day’s work
    = (A + B + C)’s 1 day’s work –
    (B + C)’s 1 day’s work
    =
    1
    -
    1
    =
    3 - 2
    =
    1
    10153030

    ∴ A alone can finish the work in 30 days.
    Aliter : Using Rule 19,
    Here, x = 12, y = 15, z = 20
    A alone can do in
    =
    2xyz
    xy + yz - zx

    =
    2 × 12 × 15 × 20
    12 × 15 + 15 × 20 - 20 × 12

    =
    24 × 300
    180 + 300 - 240

    =
    24 × 300
    = 30 days
    240