A and B can complete a piece of work in 45 and 40 days respectively. Both started to work together, but after some days A left and B alone completed the rest work in 23 days. For how many days did A work?
-
- 12 days
- 10 days
- 8 days
- 9 days
Correct Option: D
Using Rule 2,
Let A worked for x days.
A’s 1 day’s work = | 45 |
∴ A’s x day’s work= | 45 |
B’s 1 day’s work = | 40 |
∴ B’s x day’s work
= | × x = | |||
40 | 40 |
(A + B) together worked for x days.
∴ (A + B)’s x day’s work
= | + | |||
45 | 40 |
= | = | |||
360 | 360 |
∴ Remaining work
= 1 - | = | |||
360 | 360 |
This part of work, i.e.,
360 |
is completed by B alone in 23 days.
∴ | = 23 × B’s 1 day’s work | 360 |
360 |
= 23 × | = | |||
40 | 40 |
∴ 360 – 17x
= | × 360 = 207 | 40 |
∴ 17x = 360 – 207 = 153
⇒ x = | = 9 days | 17 |
Hence, A worked for 9 days.