-
A and B together can finish a work in 15 days. A and C take 2 days more to complete the same work than that of B and C. A, B and C together complete the work in 8 days. In how many days will A finish it separately?
-
- 40 days
- 24 days
-
17 1 days 7 - 20 days
Correct Option: A
(A + B)’s 1 day’s work = | 15 |
(A + B + C)’s 1 day’s work = | 8 |
∴ C’s 1 day’s work
= | - | = | = | |||||
8 | 15 | 120 | 120 |
Let (B + C) can complete the work in x days.
∴ (A + C) can complete the work in (x + 2) days.
∴ (B + C)’s 1 day’s work = | x |
(A + C)’s 1 day’s work = | x + 2 |
∴ B’s 1 day’s work
= | - | = | ||||
x | 120 | 120x |
and, A’s 1 day’s work
= | - | = | ||||
x + 2 | 120 | 120(x + 2) |
= | 120(x + 2) |
Now, A’s 1 day’s work + B’s 1 day’s work = (A + B)’s 1 day’s work
⇒ | + | = | ||||
120(x + 2) | 120x | 15 |
⇒ | = | |||
120x(x + 2) | 15 |
⇒ – 14x2 + 212x + 240 = 8x2 + 16x
⇒ 22x2 – 196x – 240 = 0
⇒ 11x2 – 98x – 120 = 0
⇒ 11x2 – 110x + 12x –120 = 0
⇒ 11x (x – 10) + 12 (x – 10)= 0
⇒ (x – 10) (11x + 12) = 0
⇒ x =10, and - | 11 |
But no. of days cannot be negative
∴ x = 10
∴ A’s 1 day’s work
= | - | |||
10 + 2 | 120 |
= | - | |||
12 | 120 |
= | = | = | ||||
120 | 120 | 40 |
∴ A alone can complete the work in 40 days.