Time and Work


  1. 5 persons can prepare an admission list in 8 days working 7 hours a day. If 2 persons join them so as to complete the work in 4 days, they need to work per day for :









  1. View Hint View Answer Discuss in Forum

    Using Rule 1,
    More persons, less working hours/day
    Less days, more working hours/day

    Persons   7 : 5
    : : 7 : x
    Days   4 : 8

    where, x is hours/days
    ∴ 7 × 4 × x = 5 × 8 × 7
    ∴ x =
    5 × 8 × 7
    = 10 hours
    7 × 4

    Correct Option: A

    Using Rule 1,
    More persons, less working hours/day
    Less days, more working hours/day

    Persons   7 : 5
    : : 7 : x
    Days   4 : 8

    where, x is hours/days
    ∴ 7 × 4 × x = 5 × 8 × 7
    ∴ x =
    5 × 8 × 7
    = 10 hours
    7 × 4


  1. If A, B and C can complete a work in 6 days. If A can work twice faster than B and thrice faster than C, then the number of days C alone can complete the work is :









  1. View Hint View Answer Discuss in Forum

    Using Rule 3,
    Let time taken by A = x days
    ∴ Time taken by B = 2x days
    Time taken by C = 3x days
    According to the question,

    1
    +
    1
    +
    1
    =
    1
    x2x3x6

    6 + 3 + 2
    =
    1
    6x6

    11
    =
    1
    6x6

    ⇒ 6x = 6 × 11
    ⇒ x =
    6 × 11
    = 11
    6

    ∴ Time taken by C alone = 3x
    = 3 × 11 = 33 days

    Correct Option: A

    Using Rule 3,
    Let time taken by A = x days
    ∴ Time taken by B = 2x days
    Time taken by C = 3x days
    According to the question,

    1
    +
    1
    +
    1
    =
    1
    x2x3x6

    6 + 3 + 2
    =
    1
    6x6

    11
    =
    1
    6x6

    ⇒ 6x = 6 × 11
    ⇒ x =
    6 × 11
    = 11
    6

    ∴ Time taken by C alone = 3x
    = 3 × 11 = 33 days



  1. A is twice as good as B and together they finish a piece of work in 16 days. The number of days taken by A alone to finish the work is









  1. View Hint View Answer Discuss in Forum

    A is twice as good as B.
    ∴ Time taken by A = x days
    Time taken by B = 2x days
    According to the question,

    1
    +
    1
    =
    1
    x2x16

    2 + 1
    =
    1
    2x16

    3
    =
    1
    2x16

    ⇒ x = 3 × 8 = 24 days

    Correct Option: D

    A is twice as good as B.
    ∴ Time taken by A = x days
    Time taken by B = 2x days
    According to the question,

    1
    +
    1
    =
    1
    x2x16

    2 + 1
    =
    1
    2x16

    3
    =
    1
    2x16

    ⇒ x = 3 × 8 = 24 days


  1. A man does double the work done by a boy in the same time. The number of days that 3 men and 4 boys will take to finish a work which can be done by 10 men in 8 days is









  1. View Hint View Answer Discuss in Forum

    According to the question,
    1 man ≡ 2 boys
    ∴ 3 men + 4 boys ≡ (3 + 2) men ≡ 5 men
    ∴ M1D1 = M2D2
    ⇒ 5 × D1 = 10 × 8

    ⇒ D1 =
    10 × 8
    = 16 days
    5

    Correct Option: B

    According to the question,
    1 man ≡ 2 boys
    ∴ 3 men + 4 boys ≡ (3 + 2) men ≡ 5 men
    ∴ M1D1 = M2D2
    ⇒ 5 × D1 = 10 × 8

    ⇒ D1 =
    10 × 8
    = 16 days
    5



  1. A works twice as fast as B. If B can complete a piece of work independently in 12 days, then what will be the number of days taken by A and B together to finish the work?









  1. View Hint View Answer Discuss in Forum

    A is twice efficient than B.
    ∴ Time taken by B = 12 days
    ⇒ Time taken by A = 6 days
    ∴ (A + B)’s 1 day’s work

    =
    1
    +
    1
    =
    2 + 1
    =
    1
    612124

    ∴ Required time = 4 days

    Correct Option: A

    A is twice efficient than B.
    ∴ Time taken by B = 12 days
    ⇒ Time taken by A = 6 days
    ∴ (A + B)’s 1 day’s work

    =
    1
    +
    1
    =
    2 + 1
    =
    1
    612124

    ∴ Required time = 4 days