Time and Work


  1. A can do a piece of work in 70 days and B is 40% more efficient than A. The number of days taken by B to do the same work is









  1. View Hint View Answer Discuss in Forum

    A : B = D2 : D2
    ⇒ 100 : 140 = D2 : 70
    ⇒ 100 × 70 = 140 × D2

    ⇒ D2 =
    100 × 70
    = 50 days.
    140

    Aliter : Using Rule 17,
    Here, x = 70, r = 40%
    Time taken by B
    = x ×
    100
    100 + R

    =
    70 × 100
    = 50 days
    100 + 40

    Correct Option: C

    A : B = D2 : D2
    ⇒ 100 : 140 = D2 : 70
    ⇒ 100 × 70 = 140 × D2

    ⇒ D2 =
    100 × 70
    = 50 days.
    140

    Aliter : Using Rule 17,
    Here, x = 70, r = 40%
    Time taken by B
    = x ×
    100
    100 + R

    =
    70 × 100
    = 50 days
    100 + 40