Time and Work


  1. A and B can do a piece of work in 15 days. B and C can do a similar work in 12 days and C and A in 10 days. How many days will A take to do the work by himself ?









  1. View Hint View Answer Discuss in Forum

    (A + B)’s 1 day’s work

    1
    ..........(i)
    15

    (B + C)’s 1 day’s work
    1
    ..........(ii)
    12

    (C + A)’s 1 day’s work
    1
    ..........(iii)
    10

    On adding all three equations,
    2 (A + B + C)’s 1 day’s work
    =
    1
    +
    1
    +
    1
    151210

    =
    4 + 5 + 6
    =
    15
    =
    1
    60604

    ∴ (A + B + C)’s 1 day’s work
    1
    ..........(iv)
    8

    By equation (iv) – (ii),
    A’s 1 day’s work
    1
    -
    1
    812

    3 - 2
    =
    1
    2424

    ∴ Required time = 24 days
    Aliter : Using Rule 19,
    A alone can do in =
    2xyz
    xy + yz - zx

    =
    2× 15 × 12 × 10
    15 × 12 + 12 × 10 - 10 × 15

    =
    2 × 3 × 12 × 10
    36 + 24 - 30

    =
    720
    24 days
    60 - 30

    Correct Option: B

    (A + B)’s 1 day’s work

    1
    ..........(i)
    15

    (B + C)’s 1 day’s work
    1
    ..........(ii)
    12

    (C + A)’s 1 day’s work
    1
    ..........(iii)
    10

    On adding all three equations,
    2 (A + B + C)’s 1 day’s work
    =
    1
    +
    1
    +
    1
    151210

    =
    4 + 5 + 6
    =
    15
    =
    1
    60604

    ∴ (A + B + C)’s 1 day’s work
    1
    ..........(iv)
    8

    By equation (iv) – (ii),
    A’s 1 day’s work
    1
    -
    1
    812

    3 - 2
    =
    1
    2424

    ∴ Required time = 24 days
    Aliter : Using Rule 19,
    A alone can do in =
    2xyz
    xy + yz - zx

    =
    2× 15 × 12 × 10
    15 × 12 + 12 × 10 - 10 × 15

    =
    2 × 3 × 12 × 10
    36 + 24 - 30

    =
    720
    24 days
    60 - 30


  1. If 35 men can finish a piece of work in 8 days, then the number of men who can do the same work in 10 days is :









  1. View Hint View Answer Discuss in Forum

    M1D1 = M2D2
    ⇒ 35 × 8 = M2 × 10

    ⇒ M2 =
    35 × 8
    = 28 men
    10

    Correct Option: B

    M1D1 = M2D2
    ⇒ 35 × 8 = M2 × 10

    ⇒ M2 =
    35 × 8
    = 28 men
    10



  1. A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days, B had to leave and A alone completed the remaining work. The whole work was completed in :









  1. View Hint View Answer Discuss in Forum

    Work done by (A + B) in 1 day

    =
    1
    +
    1
    =
    2 + 3
    =
    1
    1510306

    ∴ (A + B)’s 2 days’ work =
    2
    =
    1
    63

    Remaining work = 1 -
    1
    =
    2
    33

    This part is done by A alone.
    ∵ one work is done by A in 15 days.
    2
    work is done in 15 ×
    2
    = 10 days.
    33

    ∴ Total number of days
    = 10 + 2 = 12 days
    Aliter : Using Rule 20,
    Here, m = 15, n = 10, p =2
    A alone completed the work in
    =
    mn - p(m + n)
    days
    n

    =
    15 × 10 - 2(15 + 10)
    10

    =
    150 - 50
    = 10 days
    10

    Total time taken= 10 + 2 = 12 days

    Correct Option: C

    Work done by (A + B) in 1 day

    =
    1
    +
    1
    =
    2 + 3
    =
    1
    1510306

    ∴ (A + B)’s 2 days’ work =
    2
    =
    1
    63

    Remaining work = 1 -
    1
    =
    2
    33

    This part is done by A alone.
    ∵ one work is done by A in 15 days.
    2
    work is done in 15 ×
    2
    = 10 days.
    33

    ∴ Total number of days
    = 10 + 2 = 12 days
    Aliter : Using Rule 20,
    Here, m = 15, n = 10, p =2
    A alone completed the work in
    =
    mn - p(m + n)
    days
    n

    =
    15 × 10 - 2(15 + 10)
    10

    =
    150 - 50
    = 10 days
    10

    Total time taken= 10 + 2 = 12 days


  1. A and B can do a piece of work in 28 and 35 days respectively. They began to work together but A leaves after sometime and B completed remaining work in 17 days. After how many days did A leave ?









  1. View Hint View Answer Discuss in Forum

    Let A worked for x days.
    According to question

    x
    +
    ( x + 17 )
    = 1
    2835

    5x + 4(x + 17)
    = 1
    140

    ⇒ 5x + 4x + 68 = 140
    ⇒ 9x = 140 – 68 = 72
    ⇒ x = 8
    ∴ A worked for 8 days

    Correct Option: C

    Let A worked for x days.
    According to question

    x
    +
    ( x + 17 )
    = 1
    2835

    5x + 4(x + 17)
    = 1
    140

    ⇒ 5x + 4x + 68 = 140
    ⇒ 9x = 140 – 68 = 72
    ⇒ x = 8
    ∴ A worked for 8 days



  1. A and B working separately can do a piece of work in 10 days and 15 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed ?









  1. View Hint View Answer Discuss in Forum

    Work done by 2 (A + B) in one day

    =
    1
    +
    1
    =
    3 + 2
    =
    1
    1015306

    ∴ Work done by (A + B) in one day
    =
    1
    12

    ∴ (A + B) can complete the work in 12 days

    Correct Option: C

    Work done by 2 (A + B) in one day

    =
    1
    +
    1
    =
    3 + 2
    =
    1
    1015306

    ∴ Work done by (A + B) in one day
    =
    1
    12

    ∴ (A + B) can complete the work in 12 days