Time and Work


  1. A can complete a work in 24 days, B in 32 days and C in 64 days. They start together. A works for 6 days and leaves and B leaves 6 days before the work is finished. In how many days was the work finished?









  1. View Hint View Answer Discuss in Forum

    Let the work was completed in x days. Hence, A worked for 6 days, B worked for (x – 6) days and C worked for x days.

    Now, A’s 1 day’s work =
    1
    24

    ∴ A’s 6 days’ work
    =
    1
    × 6 =
    1
    244

    B’s 1 day’s work =
    1
    32

    ∴ B’s (x – 6) days’ work
    =
    1
    × (x - 6) =
    x - 6
    3232

    C’s 1 day’s work =
    1
    64

    ∴ C’s x days’ work
    =
    1
    × x =
    x
    6464

    1
    +
    x - 6
    +
    x
    = 1
    43264

    x - 6
    +
    x
    3264

    = 1 -
    1
    =
    3
    44

    ⇒ 3x – 12 = 48
    ⇒ 3x = 48 + 12 = 60
    ⇒ x =
    60
    = 20
    3

    Hence, the work was completed in 20 days

    Correct Option: A

    Let the work was completed in x days. Hence, A worked for 6 days, B worked for (x – 6) days and C worked for x days.

    Now, A’s 1 day’s work =
    1
    24

    ∴ A’s 6 days’ work
    =
    1
    × 6 =
    1
    244

    B’s 1 day’s work =
    1
    32

    ∴ B’s (x – 6) days’ work
    =
    1
    × (x - 6) =
    x - 6
    3232

    C’s 1 day’s work =
    1
    64

    ∴ C’s x days’ work
    =
    1
    × x =
    x
    6464

    1
    +
    x - 6
    +
    x
    = 1
    43264

    x - 6
    +
    x
    3264

    = 1 -
    1
    =
    3
    44

    ⇒ 3x – 12 = 48
    ⇒ 3x = 48 + 12 = 60
    ⇒ x =
    60
    = 20
    3

    Hence, the work was completed in 20 days


  1. A, B and C can complete a work separately in 24, 36 and 48 days respectively. They started together but C left after 4 days of start and A left 3 days before the completion of work. In how many days will the work be completed?









  1. View Hint View Answer Discuss in Forum

    Let the work be completed in x days. Therefore, A worked for x – 3 days, B for x days and C for 4 days.

    A’s 1 day’s work =
    1
    24

    B’s 1 day’s work =
    1
    36

    and, C’s 1 day’s work =
    1
    48

    ∴ (x - 3) ×
    1
    + x ×
    1
    + 4 ×
    1
    = 1
    243648

    x - 3
    +
    x
    +
    1
    = 1
    243612

    3x - 9 + 2x + 6
    = 1
    72

    ⇒ 5x – 3 = 72
    ⇒ 5x = 75
    ⇒ x =
    75
    = 15
    5

    Hence, the work was completed in 15 days.

    Correct Option: D

    Let the work be completed in x days. Therefore, A worked for x – 3 days, B for x days and C for 4 days.

    A’s 1 day’s work =
    1
    24

    B’s 1 day’s work =
    1
    36

    and, C’s 1 day’s work =
    1
    48

    ∴ (x - 3) ×
    1
    + x ×
    1
    + 4 ×
    1
    = 1
    243648

    x - 3
    +
    x
    +
    1
    = 1
    243612

    3x - 9 + 2x + 6
    = 1
    72

    ⇒ 5x – 3 = 72
    ⇒ 5x = 75
    ⇒ x =
    75
    = 15
    5

    Hence, the work was completed in 15 days.



  1. A and B together can complete a piece of work in 72 days, B and C together can complete it in 120 days, and A and C together in 90 days. In what time can A alone complete the work ?









  1. View Hint View Answer Discuss in Forum

    (A + B)’s 1 day’s work =
    1
    72

    (B + C)’s 1 day’s work =
    1
    120

    (C + A)’s 1 day’s work =
    1
    90

    Adding all three,
    2(A + B + C)’s 1 day’s work =
    1
    +
    1
    +
    1
    7212090

    2(A + B + C)’s 1 day’s work =
    5 + 3 + 4
    =
    12
    =
    1
    36036030

    ∴ (A + B + C)’s 1 day’s work =
    1
    60

    Now, A’s 1 day’s work = (A + B + C)’s 1 day’s work - (B + C)’s 1 day’s work
    A’s 1 day’s work =
    1
    -
    1
    60120

    A’s 1 day’s work =
    2 - 1
    =
    1
    120120

    ∴ A alone can complete the work in 120 days.
    Second method to solve this question ,
    Here , x = 72 , y = 120 , z = 90
    A alone can do in =
    2xyz
    xy + yz - zx

    Correct Option: C

    (A + B)’s 1 day’s work =
    1
    72

    (B + C)’s 1 day’s work =
    1
    120

    (C + A)’s 1 day’s work =
    1
    90

    Adding all three,
    2(A + B + C)’s 1 day’s work =
    1
    +
    1
    +
    1
    7212090

    2(A + B + C)’s 1 day’s work =
    5 + 3 + 4
    =
    12
    =
    1
    36036030

    ∴ (A + B + C)’s 1 day’s work =
    1
    60

    Now, A’s 1 day’s work = (A + B + C)’s 1 day’s work - (B + C)’s 1 day’s work
    A’s 1 day’s work =
    1
    -
    1
    60120

    A’s 1 day’s work =
    2 - 1
    =
    1
    120120

    ∴ A alone can complete the work in 120 days.
    Second method to solve this question ,
    Here , x = 72 , y = 120 , z = 90
    A alone can do in =
    2xyz
    xy + yz - zx

    A alone can do in =
    2 × 72 × 120 × 90
    72 × 120 + 120 × 90 - 72 × 90

    A alone can do in =
    2 × 72 × 120 × 90
    8640 + 10800 – 6480

    A alone can do in =
    144 × 10800
    = 120 days
    12960


  1. A and B together can do a piece of work in 30 days, B and C together can do it in 20 days. A starts the work and works on it for 5 days, then B takes it up and works for 15 days. Finally C finishes the work in 18 days. In how many days can C do the work when doing it separately?









  1. View Hint View Answer Discuss in Forum

    Let us denote A’s 1 day’s work by A, B’s 1 day’s work by B and C’s work by C.

    So, A + B =
    1
    30

    and B + C =
    1
    20

    Also, 5A + 15B + 18C = 1 work.
    This can be written as,
    5 (A + B) + 10 (B + C) + 8C= 1
    Substituting the values of (A + B) and (B + C) we get,
    =5 ×
    1
    +10 ×
    1
    + 8C = 1
    3020

    or
    1
    +
    1
    + 8C = 1
    62

    or 8C = 1 -
    1
    -
    1
    62

    or 8C =
    6 - 1 - 3
    6

    or 8C =
    2
    6

    or C =
    2
    =
    1
    6 × 824

    Hence, C will complete the work in 24 days.

    Correct Option: B

    Let us denote A’s 1 day’s work by A, B’s 1 day’s work by B and C’s work by C.

    So, A + B =
    1
    30

    and B + C =
    1
    20

    Also, 5A + 15B + 18C = 1 work.
    This can be written as,
    5 (A + B) + 10 (B + C) + 8C= 1
    Substituting the values of (A + B) and (B + C) we get,
    =5 ×
    1
    +10 ×
    1
    + 8C = 1
    3020

    or
    1
    +
    1
    + 8C = 1
    62

    or 8C = 1 -
    1
    -
    1
    62

    or 8C =
    6 - 1 - 3
    6

    or 8C =
    2
    6

    or C =
    2
    =
    1
    6 × 824

    Hence, C will complete the work in 24 days.



  1. A and B together can finish a work in 15 days. A and C take 2 days more to complete the same work than that of B and C. A, B and C together complete the work in 8 days. In how many days will A finish it separately?









  1. View Hint View Answer Discuss in Forum

    (A + B)’s 1 day’s work =
    1
    15

    (A + B + C)’s 1 day’s work =
    1
    8

    ∴ C’s 1 day’s work
    =
    1
    -
    1
    =
    15 - 8
    =
    7
    815120120

    Let (B + C) can complete the work in x days.
    ∴ (A + C) can complete the work in (x + 2) days.
    ∴ (B + C)’s 1 day’s work =
    1
    x

    (A + C)’s 1 day’s work =
    1
    x + 2

    ∴ B’s 1 day’s work
    =
    1
    -
    7
    =
    120 - 7x
    x120120x

    and, A’s 1 day’s work
    =
    1
    -
    7
    =
    120 - 7(x + 2)
    x + 2120120(x + 2)

    =
    106 - 7x
    120(x + 2)

    Now, A’s 1 day’s work + B’s 1 day’s work = (A + B)’s 1 day’s work
    106 - 7x
    +
    120 - 7x
    =
    1
    120(x + 2)120x15

    106x - 7x2 + 120x + 240 - 7x2 - 14x
    =
    1
    120x(x + 2)15

    ⇒ – 14x2 + 212x + 240 = 8x2 + 16x
    ⇒ 22x2 – 196x – 240 = 0
    ⇒ 11x2 – 98x – 120 = 0
    ⇒ 11x2 – 110x + 12x –120 = 0
    ⇒ 11x (x – 10) + 12 (x – 10)= 0
    ⇒ (x – 10) (11x + 12) = 0
    ⇒ x =10, and -
    12
    11

    But no. of days cannot be negative
    ∴ x = 10
    ∴ A’s 1 day’s work
    =
    1
    -
    7
    10 + 2120

    =
    1
    -
    7
    12120

    =
    10 - 7
    =
    3
    =
    1
    12012040

    ∴ A alone can complete the work in 40 days.

    Correct Option: A

    (A + B)’s 1 day’s work =
    1
    15

    (A + B + C)’s 1 day’s work =
    1
    8

    ∴ C’s 1 day’s work
    =
    1
    -
    1
    =
    15 - 8
    =
    7
    815120120

    Let (B + C) can complete the work in x days.
    ∴ (A + C) can complete the work in (x + 2) days.
    ∴ (B + C)’s 1 day’s work =
    1
    x

    (A + C)’s 1 day’s work =
    1
    x + 2

    ∴ B’s 1 day’s work
    =
    1
    -
    7
    =
    120 - 7x
    x120120x

    and, A’s 1 day’s work
    =
    1
    -
    7
    =
    120 - 7(x + 2)
    x + 2120120(x + 2)

    =
    106 - 7x
    120(x + 2)

    Now, A’s 1 day’s work + B’s 1 day’s work = (A + B)’s 1 day’s work
    106 - 7x
    +
    120 - 7x
    =
    1
    120(x + 2)120x15

    106x - 7x2 + 120x + 240 - 7x2 - 14x
    =
    1
    120x(x + 2)15

    ⇒ – 14x2 + 212x + 240 = 8x2 + 16x
    ⇒ 22x2 – 196x – 240 = 0
    ⇒ 11x2 – 98x – 120 = 0
    ⇒ 11x2 – 110x + 12x –120 = 0
    ⇒ 11x (x – 10) + 12 (x – 10)= 0
    ⇒ (x – 10) (11x + 12) = 0
    ⇒ x =10, and -
    12
    11

    But no. of days cannot be negative
    ∴ x = 10
    ∴ A’s 1 day’s work
    =
    1
    -
    7
    10 + 2120

    =
    1
    -
    7
    12120

    =
    10 - 7
    =
    3
    =
    1
    12012040

    ∴ A alone can complete the work in 40 days.