Time and Work


  1. A can do a job in 10 days and B can do the same job in 15 days. They start working together, but B leaves after 5 days. How many more days A want to finish the work ?









  1. View Hint View Answer Discuss in Forum

    Work done by A and B in 5 days

    ⇒ 5
    1
    +
    1
    = 5
    3 + 2
    101530

    = 5 ×
    5
    =
    5
    306

    Remaining work = 1 –
    5
    =
    1
    66

    ∴ Time taken by A
    =
    1
    × 10 =
    5
    days = 1
    2
    days
    633

    Correct Option: B

    Work done by A and B in 5 days

    ⇒ 5
    1
    +
    1
    = 5
    3 + 2
    101530

    = 5 ×
    5
    =
    5
    306

    Remaining work = 1 –
    5
    =
    1
    66

    ∴ Time taken by A
    =
    1
    × 10 =
    5
    days = 1
    2
    days
    633


  1. 12 men can complete a work in 90 days. 30 days after they started work, 2 men left and 8 men joined. How many days will it take to complete the remaining work ?









  1. View Hint View Answer Discuss in Forum

    Work done in 30 days = W2

    M1D1
    =
    M2D2
    W1W2

    12 × 90
    =
    12 × 30
    1W2

    ⇒ W2 =
    12 × 30
    =
    1
    12 × 903

    Remaining work = 1 –
    1
    =
    2
    33

    New number of men = 18
    M1D1
    =
    M2D2
    1W

    12 × 90
    =
    18 × D2
    12/3

    ⇒ 18 × D2 = 12 × 90 ×
    2
    = 12 × 60
    3

    ⇒ D2 =
    12 × 60
    = 40 days
    18

    Correct Option: C

    Work done in 30 days = W2

    M1D1
    =
    M2D2
    W1W2

    12 × 90
    =
    12 × 30
    1W2

    ⇒ W2 =
    12 × 30
    =
    1
    12 × 903

    Remaining work = 1 –
    1
    =
    2
    33

    New number of men = 18
    M1D1
    =
    M2D2
    1W

    12 × 90
    =
    18 × D2
    12/3

    ⇒ 18 × D2 = 12 × 90 ×
    2
    = 12 × 60
    3

    ⇒ D2 =
    12 × 60
    = 40 days
    18



  1. X can do a piece of work in 24 days. When he had worked for 4 days, Y joined him. If complete work was finished in 16 days, Y can alone finish that work in:









  1. View Hint View Answer Discuss in Forum

    Let Y alone complete the work in x days.
    According to the question,
    X’s 16 days’ work + Y’s 12 days’ work = 1

    16
    +
    12
    = 1
    24x

    2
    +
    12
    = 1
    3x

    12
    = 1 -
    2
    =
    1
    x33

    ⇒ x = 12 × 3 = 36 days

    Correct Option: C

    Let Y alone complete the work in x days.
    According to the question,
    X’s 16 days’ work + Y’s 12 days’ work = 1

    16
    +
    12
    = 1
    24x

    2
    +
    12
    = 1
    3x

    12
    = 1 -
    2
    =
    1
    x33

    ⇒ x = 12 × 3 = 36 days


  1. A certain number of men can do a work in 40 days. If there were 8 men more, it could be finished in 10 days less. How many men were there initially?









  1. View Hint View Answer Discuss in Forum

    Number of men initially = x (let)
    ∴ M1 D1 = M2 D2
    ⇒ x × 40 = (x + 8) × 30
    ⇒ 4x = 3x + 24
    ⇒ 4x – 3x = 24
    ⇒ x = 24 men
    Aliter : Using Rule 23,
    Here, D = 40, a = 8, d = 10
    Required number

    =
    a(D - d)
    men
    d

    =
    8(40 - 10)
    = 24 men
    10

    Correct Option: B

    Number of men initially = x (let)
    ∴ M1 D1 = M2 D2
    ⇒ x × 40 = (x + 8) × 30
    ⇒ 4x = 3x + 24
    ⇒ 4x – 3x = 24
    ⇒ x = 24 men
    Aliter : Using Rule 23,
    Here, D = 40, a = 8, d = 10
    Required number

    =
    a(D - d)
    men
    d

    =
    8(40 - 10)
    = 24 men
    10



  1. Raja can do a piece of work in 20 days while Ramesh can finish it in 25 days. Ramesh started working and Raja joined him after 10 days. The whole work is completed in









  1. View Hint View Answer Discuss in Forum

    Work done by Raja and Ramesh in 1 day

    =
    1
    +
    1
    =
    5 + 4
    =
    9
    2025100100

    Work done by Ramesh in 10 days
    =
    10
    =
    2
    255

    Remaining work = 1 –
    2
    =
    3
    55

    ∴ This part is done by Raja and Ramesh.
    ∴ Time taken
    =
    3
    ×
    100
    =
    20
    = 6
    2
    days.
    5933

    ∴ Required time
    = 10 + 6
    2
    = 16
    2
    days
    33

    Correct Option: B

    Work done by Raja and Ramesh in 1 day

    =
    1
    +
    1
    =
    5 + 4
    =
    9
    2025100100

    Work done by Ramesh in 10 days
    =
    10
    =
    2
    255

    Remaining work = 1 –
    2
    =
    3
    55

    ∴ This part is done by Raja and Ramesh.
    ∴ Time taken
    =
    3
    ×
    100
    =
    20
    = 6
    2
    days.
    5933

    ∴ Required time
    = 10 + 6
    2
    = 16
    2
    days
    33