Time and Work


  1. A can complete a work in ‘m’ days and B can complete it in ‘n’ days. How many days will it take to complete the work if both A and B work together ?









  1. View Hint View Answer Discuss in Forum

    A’s 1 day’s work =
    1
    m

    B’s 1 day’s work =
    1
    n

    ∴ (A + B)’s 1 day’s work =
    1
    +
    1
    mn

    Correct Option: D

    A’s 1 day’s work =
    1
    m

    B’s 1 day’s work =
    1
    n

    ∴ (A + B)’s 1 day’s work =
    1
    +
    1
    mn

    (A + B)’s 1 day’s work =
    m + n
    =
    m + n
    mnmn

    ∴ Required time =
    mn
    m + n


  1. Three men A. B and C working together can do a job in 6 hours less time than A alone, in 1 hour less time than B alone and in one half the time needed by C when working alone. Then A and B together can do the job in









  1. View Hint View Answer Discuss in Forum

    Let A, B and C together do the work in t hours.
    ∴ Time taken by A = (d + 6) hours
    Time taken by B = (t + 1) hours
    Time taken by C = 2t hours

    1
    +
    1
    +
    1
    =
    1
    t + 6t + 12tt

    1
    +
    1
    =
    1
    -
    1
    t + 6t + 1t2t

    =
    1
    2t

    1
    =
    1
    -
    1
    t + 62tt + 1

    =
    t + 1 - 2t
    2t(t + 1)

    =
    1
    =
    1 - t
    t + 62t2 + 2t

    ⇒ 2t2 + 2t = t + 6 – t2 – 6t
    ⇒ 3t2 + 7t – 6 = 0
    ⇒ 3t2 + 9t – 2t – 6 = 0
    ⇒ 3t (t + 3) – 2 (t + 3) = 0
    ⇒ (3t – 2) (t +3) = 0
    ⇒ 3t – 2 = 0 as t + 3 ≠ 0

    Correct Option: D

    Let A, B and C together do the work in t hours.
    ∴ Time taken by A = (d + 6) hours
    Time taken by B = (t + 1) hours
    Time taken by C = 2t hours

    1
    +
    1
    +
    1
    =
    1
    t + 6t + 12tt

    1
    +
    1
    =
    1
    -
    1
    t + 6t + 1t2t

    =
    1
    2t

    1
    =
    1
    -
    1
    t + 62tt + 1

    =
    t + 1 - 2t
    2t(t + 1)

    =
    1
    =
    1 - t
    t + 62t2 + 2t

    ⇒ 2t2 + 2t = t + 6 – t2 – 6t
    ⇒ 3t2 + 7t – 6 = 0
    ⇒ 3t2 + 9t – 2t – 6 = 0
    ⇒ 3t (t + 3) – 2 (t + 3) = 0
    ⇒ (3t – 2) (t +3) = 0
    ⇒ 3t – 2 = 0 as t + 3 ≠ 0
    ⇒ t =
    2
    3

    ∴ Time taken by A = 6 +
    2
    3

    =
    18 + 2
    =
    20
    hours
    33

    Time taken by B = 1 +
    2
    3

    =
    5
    hours
    3

    ∴ (A +B)’s 1 hour’s work
    =
    3
    +
    3
    205

    =
    3 + 12
    20

    =
    15
    =
    3
    204

    ∴ Required time =
    4
    hours
    3



  1. A takes three times as long as B and C together to do a job. B takes four times as long as A and C together to do the work. If all the three, working together can complete the job in 24 days, then the number of days, A alone will take to finish the job is









  1. View Hint View Answer Discuss in Forum

    Let Time taken by B and C = k days
    ∴ Time taken by A = 3k days

    ∴ Part of work done by A, B and C in 1 day =
    1
    +
    1
    =
    3 + 1
    =
    4
    k3k3k3k

    4
    =
    1
    ⇒ 3k = 4 × 24
    3k24

    Correct Option: B

    Let Time taken by B and C = k days
    ∴ Time taken by A = 3k days

    ∴ Part of work done by A, B and C in 1 day =
    1
    +
    1
    =
    3 + 1
    =
    4
    k3k3k3k

    4
    =
    1
    ⇒ 3k = 4 × 24
    3k24

    ⇒ k =
    4 × 24
    = 32 days
    3

    ∴ Time taken by A = 32 × 3 = 96 days


  1. A can do a piece of work in 4 days and B can do it in 12 days. In how many days will they finish the work, both working together ?









  1. View Hint View Answer Discuss in Forum

    A’s 1 day’s work =
    1
    4

    B’s 1 day’s work =
    1
    12

    (A + B)’s 1 day’s work =
    1
    +
    1
    412

    (A + B)’s 1 day’s work =
    4
    =
    1
    123

    ∴ Required time = 3 days
    Second method to solve this question ,

    Correct Option: D

    A’s 1 day’s work =
    1
    4

    B’s 1 day’s work =
    1
    12

    (A + B)’s 1 day’s work =
    1
    +
    1
    412

    (A + B)’s 1 day’s work =
    4
    =
    1
    123

    ∴ Required time = 3 days
    Second method to solve this question ,
    Time taken =
    xy
    days
    x + y

    Time taken =
    4 × 12
    4 + 12

    Time taken =
    48
    = 3 days
    16



  1. A can do
    1
    of a work in 10 days.
    4

    B can do
    1
    of the work in 20 days.
    3

    In how many days can both A and B together do the work ?









  1. View Hint View Answer Discuss in Forum

    A does
    1
    work in 10 days
    4

    ∴ A will do 1 work in 10 × 4 = 40 days
    Similarly, B will do the same work in 20 × 3 = 60 days
    ∴ (A + B)’s 1 day’s work =
    1
    +
    1
    4060

    =
    3 + 2
    120

    (A + B)’s 1 day’s work =
    5
    =
    1
    12024

    ∴ Required time = 24 days
    Second method to solve this question ,
    Time taken by A to finish the work = 40 days
    Time taken by B to finish the work = 60 days

    Correct Option: C

    A does
    1
    work in 10 days
    4

    ∴ A will do 1 work in 10 × 4 = 40 days
    Similarly, B will do the same work in 20 × 3 = 60 days
    ∴ (A + B)’s 1 day’s work =
    1
    +
    1
    4060

    =
    3 + 2
    120

    (A + B)’s 1 day’s work =
    5
    =
    1
    12024

    ∴ Required time = 24 days
    Second method to solve this question ,
    Time taken by A to finish the work = 40 days
    Time taken by B to finish the work = 60 days
    Total time taken =
    x × y
    days
    x + y

    Total time taken =
    40 × 60
    40 + 60

    Total time taken =
    40 × 60
    = 24 days
    100