Time and Work


  1. A can do a piece of work in 20 days which B can do in 12 days. B worked at it for 9 days. A can finish the remaining work in









  1. View Hint View Answer Discuss in Forum

    Work done by B in 9 days

    =
    9
    =
    3
    part
    124

    Remaining work
    = 1 -
    3
    =
    1
    44

    which is done by A
    ∴ Time taken by A =
    1
    × 20 = 5 days.
    4

    Correct Option: A

    Work done by B in 9 days

    =
    9
    =
    3
    part
    124

    Remaining work
    = 1 -
    3
    =
    1
    44

    which is done by A
    ∴ Time taken by A =
    1
    × 20 = 5 days.
    4


  1. A, B and C can do a piece of work in 30, 20 and 10 days respectively. A is assisted by B on one day and by C on the next day, alternately. How long would the work take to finish ?









  1. View Hint View Answer Discuss in Forum

    Work done in first two days

    =
    2
    +
    1
    +
    1
    302010

    =
    1
    +
    1
    +
    1
    152010

    =
    4 + 3 + 6
    =
    13
    6060

    Work done in first 8 days =
    52
    60

    Remaining work
    = 1 -
    52
    =
    8
    =
    2
    606015

    (A + B)’s 1 day’s work
    =
    1
    +
    1
    =
    2 + 3
    =
    3
    30206012

    ∴ Remaining work =
    2
    -
    1
    1512

    =
    8 - 5
    =
    3
    =
    1
    606020

    (A + C)’s 1 day’s work
    =
    1
    +
    1
    =
    1 + 3
    =
    2
    30103015

    ∴ Time taken =
    1
    ×
    15
    202

    =
    3
    day
    8

    Total time = 9 +
    3
    = 9
    3
    days
    88

    Correct Option: A

    Work done in first two days

    =
    2
    +
    1
    +
    1
    302010

    =
    1
    +
    1
    +
    1
    152010

    =
    4 + 3 + 6
    =
    13
    6060

    Work done in first 8 days =
    52
    60

    Remaining work
    = 1 -
    52
    =
    8
    =
    2
    606015

    (A + B)’s 1 day’s work
    =
    1
    +
    1
    =
    2 + 3
    =
    3
    30206012

    ∴ Remaining work =
    2
    -
    1
    1512

    =
    8 - 5
    =
    3
    =
    1
    606020

    (A + C)’s 1 day’s work
    =
    1
    +
    1
    =
    1 + 3
    =
    2
    30103015

    ∴ Time taken =
    1
    ×
    15
    202

    =
    3
    day
    8

    Total time = 9 +
    3
    = 9
    3
    days
    88



  1. X alone can complete a piece of work in 40 days. He worked for 8 days and left. Y alone completed the remaining work in 16 days. How long would X and Y together take to complete the work ?









  1. View Hint View Answer Discuss in Forum

    Part of the work done by X in 8 days

    =
    8
    =
    1
    405

    ∵ work done in 1 day =
    1
    40

    ∴ Remaining work = 1 -
    1
    =
    4
    55

    This part of work is done by Y in 16 days.
    ∴ Time taken by Y in doing 1 work
    =
    16 × 5
    = 20 days.
    4

    ∴ Work done by X and Y in 1 day
    =
    1
    +
    1
    =
    1 + 2
    =
    3
    40204040

    Correct Option: A

    Part of the work done by X in 8 days

    =
    8
    =
    1
    405

    ∵ work done in 1 day =
    1
    40

    ∴ Remaining work = 1 -
    1
    =
    4
    55

    This part of work is done by Y in 16 days.
    ∴ Time taken by Y in doing 1 work
    =
    16 × 5
    = 20 days.
    4

    ∴ Work done by X and Y in 1 day
    =
    1
    +
    1
    =
    1 + 2
    =
    3
    40204040


  1. A and B can do a piece of work in 12 days and 15 days respectively. They began to work together but A left after 4 days. In how many more days would B alone complete the remaining work ?









  1. View Hint View Answer Discuss in Forum

    Part of the work done by A and B in 4 days

    = 4
    1
    +
    1
    = 4
    5 + 4
    121560

    = 4 ×
    9
    =
    3
    605

    Remaining work = 1 -
    3
    =
    2
    55

    ∴ Time taken by B to complete the remaining work
    =
    2
    × 15 = 6 days
    5

    Aliter :
    Using Rule 20,
    Here, m = 12, n = 15, p = 4
    B alone do the works in
    =
    mn - p(m + n)
    m

    =
    12 × 15 - 4(12 + 15)
    12

    =
    180 - 108
    =
    72
    = 6 days
    1212

    Correct Option: C

    Part of the work done by A and B in 4 days

    = 4
    1
    +
    1
    = 4
    5 + 4
    121560

    = 4 ×
    9
    =
    3
    605

    Remaining work = 1 -
    3
    =
    2
    55

    ∴ Time taken by B to complete the remaining work
    =
    2
    × 15 = 6 days
    5

    Aliter :
    Using Rule 20,
    Here, m = 12, n = 15, p = 4
    B alone do the works in
    =
    mn - p(m + n)
    m

    =
    12 × 15 - 4(12 + 15)
    12

    =
    180 - 108
    =
    72
    = 6 days
    1212



  1. A and B together can complete a work in 12 days. A alone can complete in 20 days. If B does the work only half a day daily, then in how many days A and B together will complete the work ?









  1. View Hint View Answer Discuss in Forum

    B’s 1 day's work

    =
    1
    -
    1
    =
    5 - 3
    =
    1
    12206030

    ∴ B's
    1
    day's work =
    1
    260

    ∴ (A + B)'s 1 day's work
    =
    1
    +
    1
    =
    3 + 4
    =
    1
    20606015

    [ ∵ B works for half day daily]
    Hence, the work will be completed in 15 days.

    Correct Option: D

    B’s 1 day's work

    =
    1
    -
    1
    =
    5 - 3
    =
    1
    12206030

    ∴ B's
    1
    day's work =
    1
    260

    ∴ (A + B)'s 1 day's work
    =
    1
    +
    1
    =
    3 + 4
    =
    1
    20606015

    [ ∵ B works for half day daily]
    Hence, the work will be completed in 15 days.