  1. A can do a piece of work in 20 days which B can do in 12 days. B worked at it for 9 days. A can finish the remaining work in
    1. 5 days
    2. 7 days
    3. 11 days
    4. 3 days
Correct Option: A

Work done by B in 9 days

=
9
=
3
part
124

Remaining work
= 1 -
3
=
1
44

which is done by A
∴ Time taken by A =
1
× 20 = 5 days.
4