Time and Work


  1. A work can be completed by P and Q in 12 days, Q and R in 15 days, R and P in 20 days. In how many days P alone can finish the work?









  1. View Hint View Answer Discuss in Forum

    (P + Q)’s 1 day’s work =
    1
    .......(i)
    12

    (Q + R)’s 1 day’s work =
    1
    .......(ii)
    15

    (R + P)’s 1 day’s work =
    1
    .......(iii)
    20

    Adding all three equations,
    2 (P + Q + R)’s 1 day’s work =
    1
    +
    1
    +
    1
    121520

    Correct Option: C

    (P + Q)’s 1 day’s work =
    1
    .......(i)
    12

    (Q + R)’s 1 day’s work =
    1
    .......(ii)
    15

    (R + P)’s 1 day’s work =
    1
    .......(iii)
    20

    Adding all three equations,
    2 (P + Q + R)’s 1 day’s work =
    1
    +
    1
    +
    1
    121520

    2 (P + Q + R)’s 1 day’s work =
    5 + 4 + 3
    =
    1
    605

    ∴ (P + Q + R)’s 1 day’s work =
    1
    .......(iv)
    10

    ∴ P’s 1 day’s work =
    1
    -
    1
    1015

    P’s 1 day’s work =
    3 - 2
    =
    1
    3030

    ∴ P alone will complete the work in 30 days.


  1. A and B can complete a piece of work in 8 days, B and C can do it in 12 days, C and A can do it in 8 days. A, B and C together can complete it in









  1. View Hint View Answer Discuss in Forum

    (A + B)’s 1 day’s work =
    1
    8

    (B + C)’s 1 day’s work =
    1
    12

    (C + A)’s 1 day’s work =
    1
    8

    On adding ,
    2 (A + B + C)’s 1 day’s work =
    1
    +
    1
    +
    1
    8128

    2 (A + B + C)’s 1 day’s work =
    3 + 2 + 3
    24

    2 (A + B + C)’s 1 day’s work =
    8
    =
    1
    243

    ∴ (A + B + C)’s 1 day’s work =
    1
    6

    Hence, the work will be completed in 6 days.
    2nd Method to solve this question :

    Correct Option: C

    (A + B)’s 1 day’s work =
    1
    8

    (B + C)’s 1 day’s work =
    1
    12

    (C + A)’s 1 day’s work =
    1
    8

    On adding ,
    2 (A + B + C)’s 1 day’s work =
    1
    +
    1
    +
    1
    8128

    2 (A + B + C)’s 1 day’s work =
    3 + 2 + 3
    24

    2 (A + B + C)’s 1 day’s work =
    8
    =
    1
    243

    ∴ (A + B + C)’s 1 day’s work =
    1
    6

    Hence, the work will be completed in 6 days.
    2nd Method to solve this question :
    Time =
    2xyz
    xy + yz + zx

    Here, x = 8, y = 12; z = 8
    Time =
    2 × 8 × 12 × 8
    =
    2 × 8 × 12 × 8
    = 6 days
    96 + 96 + 64256



  1. 'A' can do a piece of work in x days and B can do the same work 3x days. To finish the work together they take 12 days. What is the value of x ?









  1. View Hint View Answer Discuss in Forum

    A's 1 day's work A = 1/x
    B's 1 day's work B = 1/3x
    (A + B)'s 1 day's work = (1/x) + (1/3x) = 4/3x
    And given one day work of both A and B = 1/12
    ⇒ 4/3x = 1/12

    Correct Option: D

    A's 1 day's work A = 1/x
    B's 1 day's work B = 1/3x
    (A + B)'s 1 day's work = (1/x) + (1/3x) = 4/3x
    And given one day work of both A and B = 1/12
    ⇒ 4/3x = 1/12
    ⇒ 3x = 48
    ⇒ x =16


  1. A and B working together; can do a piece of work in 4
    1
    hours. B and C working together
    2

    can do it in 3 hours. C and A working together can do it in 2
    1
    hours. All of them
    4
    begin the work at the same time. Find how much time they will take to finish the piece of work.









  1. View Hint View Answer Discuss in Forum

    (A + B)’s 1 hour’s work =
    2
    .......(i)
    9

    (B + C)’s 1 hour’s work =
    1
    .......(ii)
    3

    (C + A)’s 1 hour’s work =
    4
    .......(iii)
    9

    Adding all three equations,
    2 (A + B + C)’s 1 hour’s work =
    2
    +
    1
    +
    4
    939

    2 (A + B + C)’s 1 hour’s work =
    2 + 3 + 4
    = 1
    9

    ∴ A, B and C together will complete the work in 2 hours.
    Second method to solve this question ,
    Here , x = 9 / 2 , y = 3 , z = 9 / 4

    Correct Option: B

    (A + B)’s 1 hour’s work =
    2
    .......(i)
    9

    (B + C)’s 1 hour’s work =
    1
    .......(ii)
    3

    (C + A)’s 1 hour’s work =
    4
    .......(iii)
    9

    Adding all three equations,
    2 (A + B + C)’s 1 hour’s work =
    2
    +
    1
    +
    4
    939

    2 (A + B + C)’s 1 hour’s work =
    2 + 3 + 4
    = 1
    9

    ∴ A, B and C together will complete the work in 2 hours.
    Second method to solve this question ,
    Here , x = 9 / 2 , y = 3 , z = 9 / 4
    Time taken = 2 ×
    9
    × 3 ×
    9
    24
    9
    × 3 + 3 ×
    9
    +
    9
    ×
    9
    2424

    Time taken =
    ( 18 × 27 ) / 8
    { ( 27/2 ) + ( 27/4 ) + ( 81/8 ) }

    Time taken =
    18 × 27
    ×
    8
    8( 108 + 54 + 81 )

    Time taken =
    18 × 27
    = 2 hours
    243



  1. A and B together can complete a piece of work in 18 days, B and C in 24 days and A and C in 36 days. In how many days, will all of them together complete the work ?









  1. View Hint View Answer Discuss in Forum

    (A + B)’s 1 day’s work =
    1
    18

    (B + C)’s 1 day’s work =
    1
    24

    (A + C)’s 1 day’s work =
    1
    36

    Adding all three,
    2 (A + B + C)’s 1 day’s work =
    1
    +
    1
    +
    1
    182436

    2 (A + B + C)’s 1 day’s work =
    4 + 3 + 2
    =
    1
    728

    ∴ (A + B + C)’ 1 day’s work =
    1
    16

    ∴ A, B and C together will complete the work in 16 days.
    Second method to solve this question ,
    Here , x = 18 , y = 24 , z = 36
    Time taken =
    2xyz
    xy + yz + zx

    Correct Option: A

    (A + B)’s 1 day’s work =
    1
    18

    (B + C)’s 1 day’s work =
    1
    24

    (A + C)’s 1 day’s work =
    1
    36

    Adding all three,
    2 (A + B + C)’s 1 day’s work =
    1
    +
    1
    +
    1
    182436

    2 (A + B + C)’s 1 day’s work =
    4 + 3 + 2
    =
    1
    728

    ∴ (A + B + C)’ 1 day’s work =
    1
    16

    ∴ A, B and C together will complete the work in 16 days.
    Second method to solve this question ,
    Here , x = 18 , y = 24 , z = 36
    Time taken =
    2xyz
    xy + yz + zx

    Total time taken =
    2 × 18 × 24 × 36
    18 × 24 + 24 × 36 + 36 × 18

    Total time taken =
    36 × 24 × 36
    432 + 864 + 648

    Total time taken =
    31104
    = 16 days
    1944