Correct Option: B
(A + B)’s 1 hour’s work = | 2 | .......(i) |
9 |
(B + C)’s 1 hour’s work = | 1 | .......(ii) |
3 |
(C + A)’s 1 hour’s work = | 4 | .......(iii) |
9 |
Adding all three equations,
2 (A + B + C)’s 1 hour’s work = | 2 | + | 1 | + | 4 |
9 | 3 | 9 |
2 (A + B + C)’s 1 hour’s work = | 2 + 3 + 4 | = 1 |
9 |
∴ A, B and C together will complete the work in 2 hours.
Second method to solve this question ,Here , x = 9 / 2 , y = 3 , z = 9 / 4
Time taken = | | | 2 × | 9 | × 3 × | 9 | |
| | 2 | 4 | |
|
9 | × 3 + 3 × | 9 | + | 9 | × | 9 | |
2 | 4 | 2 | 4 |
Time taken = | ( 18 × 27 ) / 8 |
{ ( 27/2 ) + ( 27/4 ) + ( 81/8 ) } | |
Time taken = | 18 × 27 | × | 8 | |
8 | ( 108 + 54 + 81 ) |
Time taken = | 18 × 27 | = 2 hours |
243 |