  1. A work can be completed by P and Q in 12 days, Q and R in 15 days, R and P in 20 days. In how many days P alone can finish the work?
    1. 10 days
    2. 20 days
    3. 30 days
    4. 60 days
Correct Option: C

(P + Q)’s 1 day’s work =
1
.......(i)
12

(Q + R)’s 1 day’s work =
1
.......(ii)
15

(R + P)’s 1 day’s work =
1
.......(iii)
20

Adding all three equations,
2 (P + Q + R)’s 1 day’s work =
1
+
1
+
1
121520

2 (P + Q + R)’s 1 day’s work =
5 + 4 + 3
=
1
605

∴ (P + Q + R)’s 1 day’s work =
1
.......(iv)
10

∴ P’s 1 day’s work =
1
-
1
1015

P’s 1 day’s work =
3 - 2
=
1
3030

∴ P alone will complete the work in 30 days.