Home » Aptitude » Time and Work » Question
  1. A and B can complete a piece of work in 8 days, B and C can do it in 12 days, C and A can do it in 8 days. A, B and C together can complete it in
    1. 4 days
    2. 5 days
    3. 6 days
    4. 7 days
Correct Option: C

(A + B)’s 1 day’s work =
1
8

(B + C)’s 1 day’s work =
1
12

(C + A)’s 1 day’s work =
1
8

On adding ,
2 (A + B + C)’s 1 day’s work =
1
+
1
+
1
8128

2 (A + B + C)’s 1 day’s work =
3 + 2 + 3
24

2 (A + B + C)’s 1 day’s work =
8
=
1
243

∴ (A + B + C)’s 1 day’s work =
1
6

Hence, the work will be completed in 6 days.
2nd Method to solve this question :
Time =
2xyz
xy + yz + zx

Here, x = 8, y = 12; z = 8
Time =
2 × 8 × 12 × 8
=
2 × 8 × 12 × 8
= 6 days
96 + 96 + 64256