Time and Work


  1. A particular job can be completed by a team of 10 men in 12 days. The same job can be completed by a team of 10 women in 6 days. How many days are needed to complete the job if the two teams work together?









  1. View Hint View Answer Discuss in Forum

    According to question,

    10 men’s one day’s work =
    1
    12

    ∴ 1 man one day’s work =
    1
    =
    1
    12 × 10120

    Similarly,
    1 woman one day’s work =
    1
    =
    1
    6 × 1060

    ∴ (1 man + 1 woman)’s one day’s work =
    1
    +
    1
    12060

    (1 man + 1 woman)’s one day’s work =
    1 + 2
    =
    3
    =
    1
    12012040

    Correct Option: A

    According to question,

    10 men’s one day’s work =
    1
    12

    ∴ 1 man one day’s work =
    1
    =
    1
    12 × 10120

    Similarly,
    1 woman one day’s work =
    1
    =
    1
    6 × 1060

    ∴ (1 man + 1 woman)’s one day’s work =
    1
    +
    1
    12060

    (1 man + 1 woman)’s one day’s work =
    1 + 2
    =
    3
    =
    1
    12012040

    ∴ (10 men + 10 women)’s one day’s work =
    10
    =
    1
    404

    Therefore, both the teams can finish the whole work in 4 days.


  1. A and B can do a piece of work in 72 days. B and C can do it in 120 days, A and C can do it in 90 days. In how many days all the three together can do the work ?









  1. View Hint View Answer Discuss in Forum

    (A + B)’s 1 day’s work =
    1
    72

    (B + C)’s 1 day’s work =
    1
    120

    (C + A)’s 1 day’s work =
    1
    90

    On adding all three
    2 (A + B + C)'s 1 days work =
    1
    +
    1
    +
    1
    7212090

    2 (A + B + C)'s 1 days work =
    5 + 3 + 4
    =
    1
    36030

    ∴ (A+B+C)’s 1 day’s work =
    1
    60

    ∴ (A+B+C) will do the work in 60 days.
    Second method to solve this question ,
    Here , x = 72 , y = 120 , z = 90
    Time taken =
    2xyz
    xy + yz + zx

    Correct Option: C

    (A + B)’s 1 day’s work =
    1
    72

    (B + C)’s 1 day’s work =
    1
    120

    (C + A)’s 1 day’s work =
    1
    90

    On adding all three
    2 (A + B + C)'s 1 days work =
    1
    +
    1
    +
    1
    7212090

    2 (A + B + C)'s 1 days work =
    5 + 3 + 4
    =
    1
    36030

    ∴ (A+B+C)’s 1 day’s work =
    1
    60

    ∴ (A+B+C) will do the work in 60 days.
    Second method to solve this question ,
    Here , x = 72 , y = 120 , z = 90
    Time taken =
    2xyz
    xy + yz + zx

    Time taken =
    2 × 72 × 120 × 90
    72 × 120 +120 × 90 +72 × 90

    =
    1555200
    8640 + 10800 + 6480

    =
    1555200
    = 60 days
    25920



  1. A and B can do a work in 12 days, B and C in 15 days and C and A in 20 days. If A, B and C work together, they will complete the work in :









  1. View Hint View Answer Discuss in Forum

    According to question,
    A and B can do a work in 12 days

    ∴ (A + B)’s one day’s work =
    1
    12

    Similarly,
    (B + C)’s one day’s work =
    1
    15

    and (C + A)’s one day’s work =
    1
    20

    On adding all three,
    ∴ 2 (A + B + C)’s one days’s work =
    1
    +
    1
    +
    1
    121520

    2 (A + B + C)’s one days’s work =
    10 + 8 + 6
    =
    1
    1205

    ⇒ (A + B + C)’s one days’s work =
    1
    10

    ∴ A, B and C together can finish the whole work in 10 days.
    Second method to solve this question ,
    Here , x = 12 , y = 15 , z = 20
    Time taken =
    2xyz
    xy + yz + zx

    Correct Option: C

    According to question,
    A and B can do a work in 12 days

    ∴ (A + B)’s one day’s work =
    1
    12

    Similarly,
    (B + C)’s one day’s work =
    1
    15

    and (C + A)’s one day’s work =
    1
    20

    On adding all three,
    ∴ 2 (A + B + C)’s one days’s work =
    1
    +
    1
    +
    1
    121520

    2 (A + B + C)’s one days’s work =
    10 + 8 + 6
    =
    1
    1205

    ⇒ (A + B + C)’s one days’s work =
    1
    10

    ∴ A, B and C together can finish the whole work in 10 days.
    Second method to solve this question ,
    Here , x = 12 , y = 15 , z = 20
    Time taken =
    2xyz
    xy + yz + zx

    Time taken =
    2 × 12 × 15 × 20
    12 × 15 + 15 × 20 + 20 × 12

    Time taken =
    24 × 300
    180 + 300 + 240

    Time taken =
    7200
    = 10 days.
    720


  1. A can do a piece of work in 120 days and B can do it in 150 days. They work together for 20 days. Then B leaves and A alone continues the work. 12 days after that C joins A and the work is completed in 48 days more. In how many days can C do it if he works alone?









  1. View Hint View Answer Discuss in Forum

    A’s 1 day’s work

    =
    1
    120

    B’s 1 day’s work =
    1
    150

    (A + B)’s 1 day’s work
    =
    1
    +
    1
    =
    5 + 4
    =
    3
    120150600200

    (A + B) work together for 20 days
    Hence, (A + B)’s 20 days’ work
    = 20 ×
    3
    =
    3
    20010

    After 20 days B leaves, and A alone works for 12 days
    ∴ A’s 12 days’ work
    =
    1
    × 12=
    2
    12010

    Now, after 12 days, C joins A and the work is finished in 48 days. It means A works for 48 days more.
    ∴ A’s 48 days’ work
    =
    1
    × 48 =
    2
    1205

    ∴ Total work done by A and B together
    =
    3
    +
    1
    +
    2
    10105

    =
    3 + 1 + 4
    =
    4
    105

    ∴ Remaining work
    = 1 -
    4
    =
    1
    55

    This part of work, i.e., 1/5 is done by C in 48 days
    ∴ C’s 48 days’ work =
    1
    5

    ∴ C’s 1 day’s work
    =
    1
    =
    1
    5 × 48240

    Hence, C alone can finish the work in 240 days.

    Correct Option: C

    A’s 1 day’s work

    =
    1
    120

    B’s 1 day’s work =
    1
    150

    (A + B)’s 1 day’s work
    =
    1
    +
    1
    =
    5 + 4
    =
    3
    120150600200

    (A + B) work together for 20 days
    Hence, (A + B)’s 20 days’ work
    = 20 ×
    3
    =
    3
    20010

    After 20 days B leaves, and A alone works for 12 days
    ∴ A’s 12 days’ work
    =
    1
    × 12=
    2
    12010

    Now, after 12 days, C joins A and the work is finished in 48 days. It means A works for 48 days more.
    ∴ A’s 48 days’ work
    =
    1
    × 48 =
    2
    1205

    ∴ Total work done by A and B together
    =
    3
    +
    1
    +
    2
    10105

    =
    3 + 1 + 4
    =
    4
    105

    ∴ Remaining work
    = 1 -
    4
    =
    1
    55

    This part of work, i.e., 1/5 is done by C in 48 days
    ∴ C’s 48 days’ work =
    1
    5

    ∴ C’s 1 day’s work
    =
    1
    =
    1
    5 × 48240

    Hence, C alone can finish the work in 240 days.



  1. A can complete a work in 10 days, B can complete the same work in 20 days and C in 40 days. A starts working on the first day, B works for second day and C works for third day. Again A works for fourth day and B for fifth day and so on. If they continued working in the same way, in how many days will the work be completed?









  1. View Hint View Answer Discuss in Forum

    A’s work for the first day

    =
    1
    10

    B’s work for the second day
    =
    1
    20

    C’s work for the third day
    =
    1
    40

    Work done in 3 days by them together
    =
    1
    +
    1
    +
    1
    102040

    =
    4 + 2 + 1
    =
    7
    4040

    Hence, 7/40 part of work will be completed in 3 days.
    =
    7 × 5
    i.e
    35
    4040

    part of work will be completed in 3 × 5 or 15 days.
    Remaining work
    = 1 -
    35
    =
    5
    =
    1
    40408

    Now, A will work on 16th day.
    The remaining work after 16 days
    =
    1
    -
    1
    =
    5 - 4
    =
    1
    8104040

    Again, B will work on 17th day.
    ∵ B completes the work in 20 days.
    ∴ B will complete 1/40 part of work in
    = 20 ×
    1
    =
    1
    day
    402

    Hence, Total time taken in completion of work
    = 15 + 1 +
    1
    = 16
    1
    day
    22

    Correct Option: B

    A’s work for the first day

    =
    1
    10

    B’s work for the second day
    =
    1
    20

    C’s work for the third day
    =
    1
    40

    Work done in 3 days by them together
    =
    1
    +
    1
    +
    1
    102040

    =
    4 + 2 + 1
    =
    7
    4040

    Hence, 7/40 part of work will be completed in 3 days.
    =
    7 × 5
    i.e
    35
    4040

    part of work will be completed in 3 × 5 or 15 days.
    Remaining work
    = 1 -
    35
    =
    5
    =
    1
    40408

    Now, A will work on 16th day.
    The remaining work after 16 days
    =
    1
    -
    1
    =
    5 - 4
    =
    1
    8104040

    Again, B will work on 17th day.
    ∵ B completes the work in 20 days.
    ∴ B will complete 1/40 part of work in
    = 20 ×
    1
    =
    1
    day
    402

    Hence, Total time taken in completion of work
    = 15 + 1 +
    1
    = 16
    1
    day
    22