Time and Work
- A and B working separately can do a piece of work in 9 and 12 days respectively. If they work for a day alternately with A beginning, the work would be completed in
-
View Hint View Answer Discuss in Forum
Part of work done by A and B in first two days
= 1 + 1 = 4 + 3 = 7 9 12 36 36
Part of work done in first 10 days = 35/36Remaining work = 1 - 35 = 1 36 36
Now it is the turn of A.
∴ Time taken by A= 1 × 9 = 1 days 36 4
+= 10 1 4 10∴ Total time = 10 + 1 = 10 1 days 4 4 Correct Option: C
Part of work done by A and B in first two days
= 1 + 1 = 4 + 3 = 7 9 12 36 36
Part of work done in first 10 days = 35/36Remaining work = 1 - 35 = 1 36 36
Now it is the turn of A.
∴ Time taken by A= 1 × 9 = 1 days 36 4
+= 10 1 4 10∴ Total time = 10 + 1 = 10 1 days 4 4
- 45 men can complete a work in 16 days. Four days after they started working, 36 more men joined them. How many days will they now take to complete the remaining work ?
-
View Hint View Answer Discuss in Forum
45 men’s 4 days’ work = 1 4
Remaining work= 1 - 1 = 3 4 4 M1D1 = M2D2 W1 W2 45 × 16 = 81 × D2 1 3/4 ⇒ D2 = 45 × 16 = 6 2 days 27 × 4 3
Aliter : Using Rule 10,
Here, A = 45, a = 16
b = 4, B = 36
Required days= A(a - b) days (A + B) = 45(16 - 4) (45 + 36) = 45 × 12 81 = 20 = 6 2 days 3 3 Correct Option: C
45 men’s 4 days’ work = 1 4
Remaining work= 1 - 1 = 3 4 4 M1D1 = M2D2 W1 W2 45 × 16 = 81 × D2 1 3/4 ⇒ D2 = 45 × 16 = 6 2 days 27 × 4 3
Aliter : Using Rule 10,
Here, A = 45, a = 16
b = 4, B = 36
Required days= A(a - b) days (A + B) = 45(16 - 4) (45 + 36) = 45 × 12 81 = 20 = 6 2 days 3 3
- A can complete a piece of work in 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is
-
View Hint View Answer Discuss in Forum
(B + C)’s 2 days’ work
= 2 1 + 1 = 2 3 + 2 30 20 60 = 1 part 6 Remaining work = 1 - 1 = 5 part 6 6
∴ Time taken by A to complete this part of work= 5 × 18 = 15 days 6 Correct Option: C
(B + C)’s 2 days’ work
= 2 1 + 1 = 2 3 + 2 30 20 60 = 1 part 6 Remaining work = 1 - 1 = 5 part 6 6
∴ Time taken by A to complete this part of work= 5 × 18 = 15 days 6
- A and B alone can complete work in 9 days and18 days respectively. They worked together; however 3 days before the completion of the work A left. In how many days was the work completed ?
-
View Hint View Answer Discuss in Forum
Let the work be completed in x days.
According to the question,
A worked for (x –3) days, while B worked for x days.∴ x - 3 + x = 1 9 18 ⇒ 2x - 6 + x = 1 ⇒ 3x - 6 = 18 18
⇒ 3x = 18 + 6 = 24∵ x = 24 = 8 days 3
Aliter :
Using Rule 8,
Here, x = 9, y = 18, m = 3Total time taken = (x + m)y x + y = (9 + 3) × 18 9 + 18 = 12 × 18 = 8 days 27 Correct Option: B
Let the work be completed in x days.
According to the question,
A worked for (x –3) days, while B worked for x days.∴ x - 3 + x = 1 9 18 ⇒ 2x - 6 + x = 1 ⇒ 3x - 6 = 18 18
⇒ 3x = 18 + 6 = 24∵ x = 24 = 8 days 3
Aliter :
Using Rule 8,
Here, x = 9, y = 18, m = 3Total time taken = (x + m)y x + y = (9 + 3) × 18 9 + 18 = 12 × 18 = 8 days 27
- A and B can separately complete a piece of work in 20 days and 30 days respectively. They worked together for some time, then B left the work. If A completed the rest of the work in 10 days, then B worked for
-
View Hint View Answer Discuss in Forum
Let A and B worked together for x days
According to the question,
Part of work done by A for (x + 10) days + part of work done by B for x days = 1⇒ x + 10 + x = 1 20 30 ⇒ 3x + 30 + 2x = 1 60
⇒ 5x + 30 = 60
⇒ 5x = 30⇒ 30 = 6 days 5
Aliter :
Using Rule 20,
Here, m =20, n= 30,
π = x and time taken by A alone = 10
mn p m n n - + ()⇒ 10 = mn - p(m + n) n 10 = 30 × 20 - x(30 + 20) 30
= 600 – x 50
50x = 300 x = 6
⇒ B worked for 6 daysCorrect Option: A
Let A and B worked together for x days
According to the question,
Part of work done by A for (x + 10) days + part of work done by B for x days = 1⇒ x + 10 + x = 1 20 30 ⇒ 3x + 30 + 2x = 1 60
⇒ 5x + 30 = 60
⇒ 5x = 30⇒ 30 = 6 days 5
Aliter :
Using Rule 20,
Here, m =20, n= 30,
π = x and time taken by A alone = 10
mn p m n n - + ()⇒ 10 = mn - p(m + n) n 10 = 30 × 20 - x(30 + 20) 30
= 600 – x 50
50x = 300 x = 6
⇒ B worked for 6 days