Time and Work


  1. A and B working separately can do a piece of work in 9 and 12 days respectively. If they work for a day alternately with A beginning, the work would be completed in









  1. View Hint View Answer Discuss in Forum

    Part of work done by A and B in first two days

    =
    1
    +
    1
    =
    4 + 3
    =
    7
    9123636

    Part of work done in first 10 days = 35/36
    Remaining work = 1 -
    35
    =
    1
    3636

    Now it is the turn of A.
    ∴ Time taken by A
    =
    1
    × 9 =
    1
    days
    364

    += 10 1 4 10
    ∴ Total time = 10 +
    1
    = 10
    1
    days
    44

    Correct Option: C

    Part of work done by A and B in first two days

    =
    1
    +
    1
    =
    4 + 3
    =
    7
    9123636

    Part of work done in first 10 days = 35/36
    Remaining work = 1 -
    35
    =
    1
    3636

    Now it is the turn of A.
    ∴ Time taken by A
    =
    1
    × 9 =
    1
    days
    364

    += 10 1 4 10
    ∴ Total time = 10 +
    1
    = 10
    1
    days
    44


  1. 45 men can complete a work in 16 days. Four days after they started working, 36 more men joined them. How many days will they now take to complete the remaining work ?









  1. View Hint View Answer Discuss in Forum

    45 men’s 4 days’ work =
    1
    4

    Remaining work
    = 1 -
    1
    =
    3
    44

    M1D1
    =
    M2D2
    W1W2

    45 × 16
    =
    81 × D2
    13/4

    ⇒ D2 =
    45 × 16
    = 6
    2
    days
    27 × 43

    Aliter : Using Rule 10,
    Here, A = 45, a = 16
    b = 4, B = 36
    Required days
    =
    A(a - b)
    days
    (A + B)

    =
    45(16 - 4)
    (45 + 36)

    =
    45 × 12
    81

    =
    20
    = 6
    2
    days
    33

    Correct Option: C

    45 men’s 4 days’ work =
    1
    4

    Remaining work
    = 1 -
    1
    =
    3
    44

    M1D1
    =
    M2D2
    W1W2

    45 × 16
    =
    81 × D2
    13/4

    ⇒ D2 =
    45 × 16
    = 6
    2
    days
    27 × 43

    Aliter : Using Rule 10,
    Here, A = 45, a = 16
    b = 4, B = 36
    Required days
    =
    A(a - b)
    days
    (A + B)

    =
    45(16 - 4)
    (45 + 36)

    =
    45 × 12
    81

    =
    20
    = 6
    2
    days
    33



  1. A can complete a piece of work in 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is









  1. View Hint View Answer Discuss in Forum

    (B + C)’s 2 days’ work

    = 2
    1
    +
    1
    = 2
    3 + 2
    302060

    =
    1
    part
    6

    Remaining work = 1 -
    1
    =
    5
    part
    66

    ∴ Time taken by A to complete this part of work
    =
    5
    × 18 = 15 days
    6

    Correct Option: C

    (B + C)’s 2 days’ work

    = 2
    1
    +
    1
    = 2
    3 + 2
    302060

    =
    1
    part
    6

    Remaining work = 1 -
    1
    =
    5
    part
    66

    ∴ Time taken by A to complete this part of work
    =
    5
    × 18 = 15 days
    6


  1. A and B alone can complete work in 9 days and18 days respectively. They worked together; however 3 days before the completion of the work A left. In how many days was the work completed ?









  1. View Hint View Answer Discuss in Forum

    Let the work be completed in x days.
    According to the question,
    A worked for (x –3) days, while B worked for x days.

    x - 3
    +
    x
    = 1
    918

    2x - 6 + x
    = 1 ⇒ 3x - 6 = 18
    18

    ⇒ 3x = 18 + 6 = 24
    ∵ x =
    24
    = 8 days
    3

    Aliter :
    Using Rule 8,
    Here, x = 9, y = 18, m = 3
    Total time taken =
    (x + m)y
    x + y

    =
    (9 + 3) × 18
    9 + 18

    =
    12 × 18
    = 8 days
    27

    Correct Option: B

    Let the work be completed in x days.
    According to the question,
    A worked for (x –3) days, while B worked for x days.

    x - 3
    +
    x
    = 1
    918

    2x - 6 + x
    = 1 ⇒ 3x - 6 = 18
    18

    ⇒ 3x = 18 + 6 = 24
    ∵ x =
    24
    = 8 days
    3

    Aliter :
    Using Rule 8,
    Here, x = 9, y = 18, m = 3
    Total time taken =
    (x + m)y
    x + y

    =
    (9 + 3) × 18
    9 + 18

    =
    12 × 18
    = 8 days
    27



  1. A and B can separately complete a piece of work in 20 days and 30 days respectively. They worked together for some time, then B left the work. If A completed the rest of the work in 10 days, then B worked for









  1. View Hint View Answer Discuss in Forum

    Let A and B worked together for x days
    According to the question,
    Part of work done by A for (x + 10) days + part of work done by B for x days = 1

    x + 10
    +
    x
    = 1
    2030

    3x + 30 + 2x
    = 1
    60

    ⇒ 5x + 30 = 60
    ⇒ 5x = 30
    30
    = 6 days
    5

    Aliter :
    Using Rule 20,
    Here, m =20, n= 30,
    π = x and time taken by A alone = 10
    mn p m n n - + ()
    ⇒ 10 =
    mn - p(m + n)
    n

    10 =
    30 × 20 - x(30 + 20)
    30

    = 600 – x 50
    50x = 300 x = 6
    ⇒ B worked for 6 days

    Correct Option: A

    Let A and B worked together for x days
    According to the question,
    Part of work done by A for (x + 10) days + part of work done by B for x days = 1

    x + 10
    +
    x
    = 1
    2030

    3x + 30 + 2x
    = 1
    60

    ⇒ 5x + 30 = 60
    ⇒ 5x = 30
    30
    = 6 days
    5

    Aliter :
    Using Rule 20,
    Here, m =20, n= 30,
    π = x and time taken by A alone = 10
    mn p m n n - + ()
    ⇒ 10 =
    mn - p(m + n)
    n

    10 =
    30 × 20 - x(30 + 20)
    30

    = 600 – x 50
    50x = 300 x = 6
    ⇒ B worked for 6 days