Time and Work


  1. A sum of money is sufficient to pay A’ s wages for 21 days and B’s wages for 28 days. The same money is sufficient to pay the wages of both for :









  1. View Hint View Answer Discuss in Forum

    A's 1 day's work =
    1
    21

    B's 1 day's work =
    1
    28

    Total work done by both
    =
    1
    +
    1
    =
    4 + 3
    =
    1
    21288412

    ∴ Amount is sufficient to pay 12 days wages of both.
    Aliter : Using Rule 2,
    Here, x = 21, y = 28
    Required days
    =
    x × y
    =
    21 × 28
    x + y21 + 28

    =
    21 × 28
    = 12 days
    49

    Correct Option: D

    A's 1 day's work =
    1
    21

    B's 1 day's work =
    1
    28

    Total work done by both
    =
    1
    +
    1
    =
    4 + 3
    =
    1
    21288412

    ∴ Amount is sufficient to pay 12 days wages of both.
    Aliter : Using Rule 2,
    Here, x = 21, y = 28
    Required days
    =
    x × y
    =
    21 × 28
    x + y21 + 28

    =
    21 × 28
    = 12 days
    49


  1. A can do a piece of work in 12 days while B alone can do it in 15 days. With the help of C they can finish it in 5 days. If they are paid ₹ 960 for the whole work how much money A gets ?









  1. View Hint View Answer Discuss in Forum

    Rule 2 and Rule 25,
    Work done by A and B in 5 days

    = 5
    1
    +
    1
    = 5
    5 + 4
    121560

    =
    9
    =
    3
    124

    Time taken by C in doing
    1
    work = 5 days
    4

    ∴ C will complete in 20 days.
    ∴ Ratio of wages =
    1
    :
    1
    :
    5
    = 5 : 4 : 3
    121520

    ∴ Amount received by A
    =
    5
    × 960 = ₹ 400
    12

    Correct Option: D

    Rule 2 and Rule 25,
    Work done by A and B in 5 days

    = 5
    1
    +
    1
    = 5
    5 + 4
    121560

    =
    9
    =
    3
    124

    Time taken by C in doing
    1
    work = 5 days
    4

    ∴ C will complete in 20 days.
    ∴ Ratio of wages =
    1
    :
    1
    :
    5
    = 5 : 4 : 3
    121520

    ∴ Amount received by A
    =
    5
    × 960 = ₹ 400
    12



  1. A, B and C together earn ₹ 150 per day while A and C together earn ₹ 94 and B and C together earn ₹ 76. The daily earning of ‘C’ is









  1. View Hint View Answer Discuss in Forum

    The daily earning of ‘C’ = Daily earning of (A + C) and
    (B + C) – Daily earning of
    (A + B + C) = 94 + 76 – 150
    = ₹ 20

    Correct Option: B

    The daily earning of ‘C’ = Daily earning of (A + C) and
    (B + C) – Daily earning of
    (A + B + C) = 94 + 76 – 150
    = ₹ 20


  1. Three persons undertake to complete a piece of work for ₹ 1,200. The first person can complete the work in 8 days, second person in 12 days and third person in 16 days. They complete the work with the help of a fourth person in 3 days. What does the fourth person get?









  1. View Hint View Answer Discuss in Forum

    Rule 3 and Rule 25,
    If the fourth person completes the work in x days, then

    3
    +
    3
    +
    3
    +
    3
    = 1
    81216x

    1
    =
    1
    -
    1
    -
    1
    -
    1
    x381216

    =
    16 - 6 - 4 - 3
    =
    1
    4816

    ∴ x = 16
    ∴ Ratio of wages
    =
    1
    :
    1
    :
    1
    :
    1
    = 6 : 4 : 3 : 3
    8121616

    Sum of ratios = 6 + 4 + 3 + 3 = 16
    ∴ Fourth person’s share
    =
    3
    × 1200 = ₹ 225
    12

    Correct Option: C

    Rule 3 and Rule 25,
    If the fourth person completes the work in x days, then

    3
    +
    3
    +
    3
    +
    3
    = 1
    81216x

    1
    =
    1
    -
    1
    -
    1
    -
    1
    x381216

    =
    16 - 6 - 4 - 3
    =
    1
    4816

    ∴ x = 16
    ∴ Ratio of wages
    =
    1
    :
    1
    :
    1
    :
    1
    = 6 : 4 : 3 : 3
    8121616

    Sum of ratios = 6 + 4 + 3 + 3 = 16
    ∴ Fourth person’s share
    =
    3
    × 1200 = ₹ 225
    12



  1. A and B working separately can do a piece of work in 9 and 15 days respectively. If they work for a day alternately, with A beginning, then the work will be completed in









  1. View Hint View Answer Discuss in Forum

    A’s 1 day’s work =
    1
    9

    B’s 1 day’s work =
    1
    15

    Work done in first 2 days = A’s 1 day’s work + B’s 1 day’s work
    Work done in first 2 days =
    1
    +
    1
    915

    Work done in first 2 days =
    5 + 3
    =
    8
    4545

    ∴ Work done in first 10 days =
    8 × 5
    =
    8
    459

    Remaining work = 1 –
    8
    =
    1
    99

    Now, it is turn of ‘A’ for the eleventh day.

    Correct Option: B

    A’s 1 day’s work =
    1
    9

    B’s 1 day’s work =
    1
    15

    Work done in first 2 days = A’s 1 day’s work + B’s 1 day’s work
    Work done in first 2 days =
    1
    +
    1
    915

    Work done in first 2 days =
    5 + 3
    =
    8
    4545

    ∴ Work done in first 10 days =
    8 × 5
    =
    8
    459

    Remaining work = 1 –
    8
    =
    1
    99

    Now, it is turn of ‘A’ for the eleventh day.
    ∴ Time taken by ‘A’ in doing
    1
    work
    9

    =
    1
    × 9 = 1 day
    9

    ∴ Required time = 10 + 1 = 11 days