Three persons undertake to complete a piece of work for ₹ 1,200. The first person can complete the work in 8 days, second person in 12 days and third person in 16 days. They complete the work with the help of a fourth person in 3 days. What does the fourth person get?
-
- ₹ 180
- ₹ 200
- ₹ 225
- ₹ 250
Correct Option: C
Rule 3 and Rule 25,
If the fourth person completes the work in x days, then
+ | + | + | = 1 | |||||
8 | 12 | 16 | x |
⇒ | = | - | - | - | ||||||
x | 3 | 8 | 12 | 16 |
= | = | |||
48 | 16 |
∴ x = 16
∴ Ratio of wages
= | : | : | : | = 6 : 4 : 3 : 3 | ||||
8 | 12 | 16 | 16 |
Sum of ratios = 6 + 4 + 3 + 3 = 16
∴ Fourth person’s share
= | × 1200 = ₹ 225 | 12 |