Home » Aptitude » Time and Work » Question
  1. Three persons undertake to complete a piece of work for ₹ 1,200. The first person can complete the work in 8 days, second person in 12 days and third person in 16 days. They complete the work with the help of a fourth person in 3 days. What does the fourth person get?
    1. ₹ 180
    2. ₹ 200
    3. ₹ 225
    4. ₹ 250
Correct Option: C

Rule 3 and Rule 25,
If the fourth person completes the work in x days, then

3
+
3
+
3
+
3
= 1
81216x

1
=
1
-
1
-
1
-
1
x381216

=
16 - 6 - 4 - 3
=
1
4816

∴ x = 16
∴ Ratio of wages
=
1
:
1
:
1
:
1
= 6 : 4 : 3 : 3
8121616

Sum of ratios = 6 + 4 + 3 + 3 = 16
∴ Fourth person’s share
=
3
× 1200 = ₹ 225
12