A can do a piece of work in 16 days and B in 24 days. They take the help of C and three together finish the work in 6 days. If the total remuneration for the work is ₹ 400. The amount (in rupees)each will receive, in proportion, to do the work is
-
- A : 150, B : 100, C : 150
- A : 100, B : 150, C : 150
- A : 150, B : 150, C : 100
- A : 100, B : 150, C : 100
Correct Option: A
Rule 3 and Rule 25,
If C alone completes the work in x days, then
| = | + | + | = | |||||
| 16 | 24 | x | 6 |
| ⇒ | = | - | - | |||||
| x | 6 | 16 | 24 |
| = | = | |||
| 48 | 16 |
⇒ x = 16 days
∴ Ratio of their remuneration
| = | : | : | = 3 : 2 : 3 | |||
| 16 | 24 | 16 |
∴ A’s remuneration
| = | × 400 = ₹ 150 | 8 |
B’s remuneration
| = | × 400 = ₹ 100 | 8 |
C’s remuneration
| = | × 400 = ₹ 150 | 8 |
⇒ A : 150, B : 100, C : 150