  1. A and B working separately can do a piece of work in 9 and 15 days respectively. If they work for a day alternately, with A beginning, then the work will be completed in
    1. 10 days
    2. 11 days
    3. 9 days
    4. 12 days
Correct Option: B

A’s 1 day’s work =
1
9

B’s 1 day’s work =
1
15

Work done in first 2 days = A’s 1 day’s work + B’s 1 day’s work
Work done in first 2 days =
1
+
1
915

Work done in first 2 days =
5 + 3
=
8
4545

∴ Work done in first 10 days =
8 × 5
=
8
459

Remaining work = 1 –
8
=
1
99

Now, it is turn of ‘A’ for the eleventh day.
∴ Time taken by ‘A’ in doing
1
work
9

=
1
× 9 = 1 day
9

∴ Required time = 10 + 1 = 11 days