Time and Work


  1. If 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do the same in 2 days, then the time taken by 15 men and 20 boys to do the same type of work will be :









  1. View Hint View Answer Discuss in Forum

    According to question,
    (6M + 8B) × 10 = (26M + 48B) × 2
    ∴ 60M + 80B = 52M + 96B
    or, 1M = 2B
    ∴ 15M + 20B = (30 + 20)B
    = 50 boys and 6M + 8B
    = (12 + 8) boys = 20 boys
    ∵ 20 boys can finish the work in 10 days
    ∴ 50 boys can finish the work in

    20 × 10
    days = 4 days
    50

    Aliter : Using Rule 11,
    A1 = 6, B1 = 8, D1 = 10
    A2 = 26, B2 = 48, D2 = 2
    A3 = 15, B3 = 20
    Required time
    =
    D1D2(A1B2 - B1A2
    days
    D1(A1B3 - A3B1) - D2(A2B3 - A3B2)

    =
    10 × 2(6 × 48 - 8 × 26)
    days
    10(6 × 20 - 15 × 8) - 2(26 × 20 - 15 × 48)

    =
    20(288 - 208)
    10(120 - 120) - 2(520 - 720)

    =
    20 × 80
    = 4 days
    400

    Correct Option: B

    According to question,
    (6M + 8B) × 10 = (26M + 48B) × 2
    ∴ 60M + 80B = 52M + 96B
    or, 1M = 2B
    ∴ 15M + 20B = (30 + 20)B
    = 50 boys and 6M + 8B
    = (12 + 8) boys = 20 boys
    ∵ 20 boys can finish the work in 10 days
    ∴ 50 boys can finish the work in

    20 × 10
    days = 4 days
    50

    Aliter : Using Rule 11,
    A1 = 6, B1 = 8, D1 = 10
    A2 = 26, B2 = 48, D2 = 2
    A3 = 15, B3 = 20
    Required time
    =
    D1D2(A1B2 - B1A2
    days
    D1(A1B3 - A3B1) - D2(A2B3 - A3B2)

    =
    10 × 2(6 × 48 - 8 × 26)
    days
    10(6 × 20 - 15 × 8) - 2(26 × 20 - 15 × 48)

    =
    20(288 - 208)
    10(120 - 120) - 2(520 - 720)

    =
    20 × 80
    = 4 days
    400


  1. A and B together can complete a piece of work in 12 days. They worked together for 5 days and then A alone finished the rest of the work in 14 days. A alone can complete the work in









  1. View Hint View Answer Discuss in Forum

    ∵ (A + B)’s 1 day’s work =
    1
    12

    ∴ (A + B)’s 5 days’ work =
    5
    12

    Remaining work = 1 –
    5
    =
    7
    1212

    ∵ A does
    7
    work in 14 days
    12

    ∴ A will do 1 work in =
    14 × 12
    = 24 days;
    7

    Correct Option: A

    ∵ (A + B)’s 1 day’s work =
    1
    12

    ∴ (A + B)’s 5 days’ work =
    5
    12

    Remaining work = 1 –
    5
    =
    7
    1212

    ∵ A does
    7
    work in 14 days
    12

    ∴ A will do 1 work in =
    14 × 12
    = 24 days;
    7



  1. A can do a work in 15 days and B in 20 days.If they together work on it for 4 days, then the fraction of the work that is left is:









  1. View Hint View Answer Discuss in Forum

    Using basics of Rule 2,

    A’s work per da =
    1
    15

    B’s work per day =
    1
    20

    (A+ B)’s work per day
    =
    1
    +
    1
    =
    4 + 3
    =
    1
    15206060

    ∴ (A + B)’s work in 4 days
    = 4 ×
    7
    =
    7
    6015

    Left work = 1 -
    7
    15

    =
    15 - 7
    =
    8
    1515

    Correct Option: A

    Using basics of Rule 2,

    A’s work per da =
    1
    15

    B’s work per day =
    1
    20

    (A+ B)’s work per day
    =
    1
    +
    1
    =
    4 + 3
    =
    1
    15206060

    ∴ (A + B)’s work in 4 days
    = 4 ×
    7
    =
    7
    6015

    Left work = 1 -
    7
    15

    =
    15 - 7
    =
    8
    1515


  1. A and B can do a piece of work in 72 days, B and C can do it in 120 days, and A and C can do it in 90 days. When A, B and C work together, how much work is finished by them in 3 days.









  1. View Hint View Answer Discuss in Forum

    Using basics of Rule 5,

    (A + B)’s 1 day’s work =
    1
    72

    (B + C)’s 1 day’s work =
    1
    120

    (C + A)’s 1 day’s work =
    1
    90

    On adding all three,
    2 (A + B + C)’s 1 day’s work,
    =
    1
    +
    1
    +
    1
    7212090

    =
    5 + 3 + 4
    =
    1
    36030

    ∴ (A + B + C)’s 1 day’s work
    =
    1
    60

    ∴ (A + B + C)’s 3 days’ work
    =
    3
    =
    1
    6020

    Correct Option: C

    Using basics of Rule 5,

    (A + B)’s 1 day’s work =
    1
    72

    (B + C)’s 1 day’s work =
    1
    120

    (C + A)’s 1 day’s work =
    1
    90

    On adding all three,
    2 (A + B + C)’s 1 day’s work,
    =
    1
    +
    1
    +
    1
    7212090

    =
    5 + 3 + 4
    =
    1
    36030

    ∴ (A + B + C)’s 1 day’s work
    =
    1
    60

    ∴ (A + B + C)’s 3 days’ work
    =
    3
    =
    1
    6020



  1. P can complete 1/4 of a work in 10 days, Q can complete 40% of the same work in 15 days, R, completes 1/3 of the work in 13 days and S, 1/6 of the work in 7 days. Who will be able to complete the work first ?









  1. View Hint View Answer Discuss in Forum

    Time taken by P in completing 1 work = 10 × 4 = 40 days
    Time taken by Q in completing 1 work

    =
    15 × 5
    =
    75
    days
    22

    Time taken by R in completing 1
    work = 13 × 3 = 39 days
    Time taken by S in completing 1
    work = 7 × 6 = 42 days
    Clearly, Q took the least time i.e.
    75
    or 37
    1
    days
    22

    Correct Option: B

    Time taken by P in completing 1 work = 10 × 4 = 40 days
    Time taken by Q in completing 1 work

    =
    15 × 5
    =
    75
    days
    22

    Time taken by R in completing 1
    work = 13 × 3 = 39 days
    Time taken by S in completing 1
    work = 7 × 6 = 42 days
    Clearly, Q took the least time i.e.
    75
    or 37
    1
    days
    22