Time and Work
- If 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do the same in 2 days, then the time taken by 15 men and 20 boys to do the same type of work will be :
-
View Hint View Answer Discuss in Forum
According to question,
(6M + 8B) × 10 = (26M + 48B) × 2
∴ 60M + 80B = 52M + 96B
or, 1M = 2B
∴ 15M + 20B = (30 + 20)B
= 50 boys and 6M + 8B
= (12 + 8) boys = 20 boys
∵ 20 boys can finish the work in 10 days
∴ 50 boys can finish the work in20 × 10 days = 4 days 50
Aliter : Using Rule 11,
A1 = 6, B1 = 8, D1 = 10
A2 = 26, B2 = 48, D2 = 2
A3 = 15, B3 = 20
Required time= D1D2(A1B2 - B1A2 days D1(A1B3 - A3B1) - D2(A2B3 - A3B2) = 10 × 2(6 × 48 - 8 × 26) days 10(6 × 20 - 15 × 8) - 2(26 × 20 - 15 × 48) = 20(288 - 208) 10(120 - 120) - 2(520 - 720) = 20 × 80 = 4 days 400 Correct Option: B
According to question,
(6M + 8B) × 10 = (26M + 48B) × 2
∴ 60M + 80B = 52M + 96B
or, 1M = 2B
∴ 15M + 20B = (30 + 20)B
= 50 boys and 6M + 8B
= (12 + 8) boys = 20 boys
∵ 20 boys can finish the work in 10 days
∴ 50 boys can finish the work in20 × 10 days = 4 days 50
Aliter : Using Rule 11,
A1 = 6, B1 = 8, D1 = 10
A2 = 26, B2 = 48, D2 = 2
A3 = 15, B3 = 20
Required time= D1D2(A1B2 - B1A2 days D1(A1B3 - A3B1) - D2(A2B3 - A3B2) = 10 × 2(6 × 48 - 8 × 26) days 10(6 × 20 - 15 × 8) - 2(26 × 20 - 15 × 48) = 20(288 - 208) 10(120 - 120) - 2(520 - 720) = 20 × 80 = 4 days 400
- A and B together can complete a piece of work in 12 days. They worked together for 5 days and then A alone finished the rest of the work in 14 days. A alone can complete the work in
-
View Hint View Answer Discuss in Forum
∵ (A + B)’s 1 day’s work = 1 12 ∴ (A + B)’s 5 days’ work = 5 12 Remaining work = 1 – 5 = 7 12 12 ∵ A does 7 work in 14 days 12 ∴ A will do 1 work in = 14 × 12 = 24 days; 7 Correct Option: A
∵ (A + B)’s 1 day’s work = 1 12 ∴ (A + B)’s 5 days’ work = 5 12 Remaining work = 1 – 5 = 7 12 12 ∵ A does 7 work in 14 days 12 ∴ A will do 1 work in = 14 × 12 = 24 days; 7
- A can do a work in 15 days and B in 20 days.If they together work on it for 4 days, then the fraction of the work that is left is:
-
View Hint View Answer Discuss in Forum
Using basics of Rule 2,
A’s work per da = 1 15 B’s work per day = 1 20
(A+ B)’s work per day= 1 + 1 = 4 + 3 = 1 15 20 60 60
∴ (A + B)’s work in 4 days= 4 × 7 = 7 60 15 Left work = 1 - 7 15 = 15 - 7 = 8 15 15 Correct Option: A
Using basics of Rule 2,
A’s work per da = 1 15 B’s work per day = 1 20
(A+ B)’s work per day= 1 + 1 = 4 + 3 = 1 15 20 60 60
∴ (A + B)’s work in 4 days= 4 × 7 = 7 60 15 Left work = 1 - 7 15 = 15 - 7 = 8 15 15
- A and B can do a piece of work in 72 days, B and C can do it in 120 days, and A and C can do it in 90 days. When A, B and C work together, how much work is finished by them in 3 days.
-
View Hint View Answer Discuss in Forum
Using basics of Rule 5,
(A + B)’s 1 day’s work = 1 72 (B + C)’s 1 day’s work = 1 120 (C + A)’s 1 day’s work = 1 90
On adding all three,
2 (A + B + C)’s 1 day’s work,= 1 + 1 + 1 72 120 90 = 5 + 3 + 4 = 1 360 30
∴ (A + B + C)’s 1 day’s work= 1 60
∴ (A + B + C)’s 3 days’ work= 3 = 1 60 20 Correct Option: C
Using basics of Rule 5,
(A + B)’s 1 day’s work = 1 72 (B + C)’s 1 day’s work = 1 120 (C + A)’s 1 day’s work = 1 90
On adding all three,
2 (A + B + C)’s 1 day’s work,= 1 + 1 + 1 72 120 90 = 5 + 3 + 4 = 1 360 30
∴ (A + B + C)’s 1 day’s work= 1 60
∴ (A + B + C)’s 3 days’ work= 3 = 1 60 20
- P can complete 1/4 of a work in 10 days, Q can complete 40% of the same work in 15 days, R, completes 1/3 of the work in 13 days and S, 1/6 of the work in 7 days. Who will be able to complete the work first ?
-
View Hint View Answer Discuss in Forum
Time taken by P in completing 1 work = 10 × 4 = 40 days
Time taken by Q in completing 1 work= 15 × 5 = 75 days 2 2
Time taken by R in completing 1
work = 13 × 3 = 39 days
Time taken by S in completing 1
work = 7 × 6 = 42 days
Clearly, Q took the least time i.e.75 or 37 1 days 2 2 Correct Option: B
Time taken by P in completing 1 work = 10 × 4 = 40 days
Time taken by Q in completing 1 work= 15 × 5 = 75 days 2 2
Time taken by R in completing 1
work = 13 × 3 = 39 days
Time taken by S in completing 1
work = 7 × 6 = 42 days
Clearly, Q took the least time i.e.75 or 37 1 days 2 2