  1. If 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do the same in 2 days, then the time taken by 15 men and 20 boys to do the same type of work will be :
    1. 5 days
    2. 4 days
    3. 6 days
    4. 7 days
Correct Option: B

According to question,
(6M + 8B) × 10 = (26M + 48B) × 2
∴ 60M + 80B = 52M + 96B
or, 1M = 2B
∴ 15M + 20B = (30 + 20)B
= 50 boys and 6M + 8B
= (12 + 8) boys = 20 boys
∵ 20 boys can finish the work in 10 days
∴ 50 boys can finish the work in

20 × 10
days = 4 days
50

Aliter : Using Rule 11,
A1 = 6, B1 = 8, D1 = 10
A2 = 26, B2 = 48, D2 = 2
A3 = 15, B3 = 20
Required time
=
D1D2(A1B2 - B1A2
days
D1(A1B3 - A3B1) - D2(A2B3 - A3B2)

=
10 × 2(6 × 48 - 8 × 26)
days
10(6 × 20 - 15 × 8) - 2(26 × 20 - 15 × 48)

=
20(288 - 208)
10(120 - 120) - 2(520 - 720)

=
20 × 80
= 4 days
400