A and B can do a piece of work in 72 days, B and C can do it in 120 days, and A and C can do it in 90 days. When A, B and C work together, how much work is finished by them in 3 days.
-
-
1 40 -
1 30 -
1 20 -
1 10
-
Correct Option: C
Using basics of Rule 5,
(A + B)’s 1 day’s work = | 72 |
(B + C)’s 1 day’s work = | 120 |
(C + A)’s 1 day’s work = | 90 |
On adding all three,
2 (A + B + C)’s 1 day’s work,
= | + | + | ||||
72 | 120 | 90 |
= | = | |||
360 | 30 |
∴ (A + B + C)’s 1 day’s work
= | 60 |
∴ (A + B + C)’s 3 days’ work
= | = | |||
60 | 20 |