Time and Work
- Working 8 hours a day, Anu can copy a book in 18 days. How many hours a day should she work so as to finish the work in 12 days ?
-
View Hint View Answer Discuss in Forum
⇒ 12 = 8 18 x
where x is hours/days
⇒ 12x = 18 × 8⇒ x = 18 × 8 = 12 hours 12
Aliter : Using Rule 1,
Here, M1 = 1, D1= 18, T1 = 8
M2 = 1, D2 = 12, T2 = ?
M1D1T1 = M2D2T2
1 × 18 × 8 = 1 × 12 × T2T2 = 18 × 8 = 12 hours 12 Correct Option: A
⇒ 12 = 8 18 x
where x is hours/days
⇒ 12x = 18 × 8⇒ x = 18 × 8 = 12 hours 12
Aliter : Using Rule 1,
Here, M1 = 1, D1= 18, T1 = 8
M2 = 1, D2 = 12, T2 = ?
M1D1T1 = M2D2T2
1 × 18 × 8 = 1 × 12 × T2T2 = 18 × 8 = 12 hours 12
- A contractor undertook to finish a work in 92 days and employed 110 men. After 48 days, he found that he had already done 3/5 part of the work, the number of men he can withdraw so that the work may still be finished in time is :
-
View Hint View Answer Discuss in Forum
Using Rule 1,
M1D1 = M2D2 W1 W2 ⇒ 110 × 48 = M2 × 44 3 2 5 5
⇒ M2 × 44 × 3 = 110 × 48 × 2⇒ M2 = 110 × 48 × 2 = 80 44 × 3
∴ Number of men can be withdrawn
= 110 – 80 = 30Correct Option: D
Using Rule 1,
M1D1 = M2D2 W1 W2 ⇒ 110 × 48 = M2 × 44 3 2 5 5
⇒ M2 × 44 × 3 = 110 × 48 × 2⇒ M2 = 110 × 48 × 2 = 80 44 × 3
∴ Number of men can be withdrawn
= 110 – 80 = 30
- A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. The number of additional men that should be appointed so that the whole work will be finished in time is :
-
View Hint View Answer Discuss in Forum
Using Rule 1,
200 men do 1 work in 50 days. 4 ∴ M1D1 = M2D2 W1 W2 ⇒ 200 × 50 = M2 × 100 1 3 4 4
⇒ M2 × 100 = 200 × 50 × 3
⇒ M2 = 300
∴ Additional men = 100Correct Option: B
Using Rule 1,
200 men do 1 work in 50 days. 4 ∴ M1D1 = M2D2 W1 W2 ⇒ 200 × 50 = M2 × 100 1 3 4 4
⇒ M2 × 100 = 200 × 50 × 3
⇒ M2 = 300
∴ Additional men = 100
- A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work.
How many men can be discharged now so that the work may finish in time ?
-
View Hint View Answer Discuss in Forum
Using Rule 1,
Remaining work = 1 - 2 = 1 3 3
Remaining days = 124–64= 60∴ M1D1 = M2D2 W1 W2 ⇒ 120 × 64 = M2 × 60 2 1 3 3 ⇒ M2 = 120 × 64 = 64 2 × 60
∴ No. of men can be discharged
= 120 – 64 = 56 menCorrect Option: B
Using Rule 1,
Remaining work = 1 - 2 = 1 3 3
Remaining days = 124–64= 60∴ M1D1 = M2D2 W1 W2 ⇒ 120 × 64 = M2 × 60 2 1 3 3 ⇒ M2 = 120 × 64 = 64 2 × 60
∴ No. of men can be discharged
= 120 – 64 = 56 men
- If 7 men working 7 hrs a day for each of 7 days produce 7 units of work, then the units of work produced by 5 men working 5 hrs a day for each of 5 days is
-
View Hint View Answer Discuss in Forum
Using Rule 1,
∴ M1D1T1 = M2D2T2 W1 W2 ⇒ 7 × 7 × 7 = 5 × 5 × 5 7 W2
⇒ 49 × W2 = 125⇒ W2 = 125 49 Correct Option: B
Using Rule 1,
∴ M1D1T1 = M2D2T2 W1 W2 ⇒ 7 × 7 × 7 = 5 × 5 × 5 7 W2
⇒ 49 × W2 = 125⇒ W2 = 125 49