Time and Work


  1. Working 8 hours a day, Anu can copy a book in 18 days. How many hours a day should she work so as to finish the work in 12 days ?









  1. View Hint View Answer Discuss in Forum


    12
    =
    8
    18x

    where x is hours/days
    ⇒ 12x = 18 × 8
    ⇒ x =
    18 × 8
    = 12 hours
    12

    Aliter : Using Rule 1,
    Here, M1 = 1, D1= 18, T1 = 8
    M2 = 1, D2 = 12, T2 = ?
    M1D1T1 = M2D2T2
    1 × 18 × 8 = 1 × 12 × T2
    T2 =
    18 × 8
    = 12 hours
    12

    Correct Option: A


    12
    =
    8
    18x

    where x is hours/days
    ⇒ 12x = 18 × 8
    ⇒ x =
    18 × 8
    = 12 hours
    12

    Aliter : Using Rule 1,
    Here, M1 = 1, D1= 18, T1 = 8
    M2 = 1, D2 = 12, T2 = ?
    M1D1T1 = M2D2T2
    1 × 18 × 8 = 1 × 12 × T2
    T2 =
    18 × 8
    = 12 hours
    12


  1. A contractor undertook to finish a work in 92 days and employed 110 men. After 48 days, he found that he had already done 3/5 part of the work, the number of men he can withdraw so that the work may still be finished in time is :









  1. View Hint View Answer Discuss in Forum

    Using Rule 1,

    M1D1
    =
    M2D2
    W1W2

    110 × 48
    =
    M2 × 44
    3
    2
    55

    ⇒ M2 × 44 × 3 = 110 × 48 × 2
    ⇒ M2 =
    110 × 48 × 2
    = 80
    44 × 3

    ∴ Number of men can be withdrawn
    = 110 – 80 = 30

    Correct Option: D

    Using Rule 1,

    M1D1
    =
    M2D2
    W1W2

    110 × 48
    =
    M2 × 44
    3
    2
    55

    ⇒ M2 × 44 × 3 = 110 × 48 × 2
    ⇒ M2 =
    110 × 48 × 2
    = 80
    44 × 3

    ∴ Number of men can be withdrawn
    = 110 – 80 = 30



  1. A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. The number of additional men that should be appointed so that the whole work will be finished in time is :









  1. View Hint View Answer Discuss in Forum

    Using Rule 1,

    200 men do
    1
    work in 50 days.
    4

    M1D1
    =
    M2D2
    W1W2

    200 × 50
    =
    M2 × 100
    1
    3
    44

    ⇒ M2 × 100 = 200 × 50 × 3
    ⇒ M2 = 300
    ∴ Additional men = 100

    Correct Option: B

    Using Rule 1,

    200 men do
    1
    work in 50 days.
    4

    M1D1
    =
    M2D2
    W1W2

    200 × 50
    =
    M2 × 100
    1
    3
    44

    ⇒ M2 × 100 = 200 × 50 × 3
    ⇒ M2 = 300
    ∴ Additional men = 100


  1. A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work.
    How many men can be discharged now so that the work may finish in time ?









  1. View Hint View Answer Discuss in Forum

    Using Rule 1,

    Remaining work = 1 -
    2
    =
    1
    33

    Remaining days = 124–64= 60
    M1D1
    =
    M2D2
    W1W2

    120 × 64
    =
    M2 × 60
    2
    1
    33

    ⇒ M2 =
    120 × 64
    = 64
    2 × 60

    ∴ No. of men can be discharged
    = 120 – 64 = 56 men

    Correct Option: B

    Using Rule 1,

    Remaining work = 1 -
    2
    =
    1
    33

    Remaining days = 124–64= 60
    M1D1
    =
    M2D2
    W1W2

    120 × 64
    =
    M2 × 60
    2
    1
    33

    ⇒ M2 =
    120 × 64
    = 64
    2 × 60

    ∴ No. of men can be discharged
    = 120 – 64 = 56 men



  1. If 7 men working 7 hrs a day for each of 7 days produce 7 units of work, then the units of work produced by 5 men working 5 hrs a day for each of 5 days is









  1. View Hint View Answer Discuss in Forum

    Using Rule 1,

    M1D1T1
    =
    M2D2T2
    W1W2

    7 × 7 × 7
    =
    5 × 5 × 5
    7W2

    ⇒ 49 × W2 = 125
    ⇒ W2 =
    125
    49

    Correct Option: B

    Using Rule 1,

    M1D1T1
    =
    M2D2T2
    W1W2

    7 × 7 × 7
    =
    5 × 5 × 5
    7W2

    ⇒ 49 × W2 = 125
    ⇒ W2 =
    125
    49