Time and Work


  1. A can do a piece of work in 18 days and B in 12 days. They began the work together, but B left the work 3 days before its completion. In how many days, in all, was the work completed?









  1. View Hint View Answer Discuss in Forum

    Let the work be finished in x days.
    According to the question, A worked for x days while B worked for (x – 3) days

    x
    +
    x - 3
    = 1
    1812

    2x + 3x - 9
    = 1
    36

    ⇒ 5x – 9 = 36
    ↠ 5x = 45
    ⇒ x =
    45
    = 9
    5

    Hence, the work was completed in 9 days.
    Aliter :
    Using Rule 8,
    Here, x = 18, y = 12, m = 3
    Total time taken =
    y + m
    x
    x + y

    =
    12 + 3
    × 18 = 9 days
    18 + 12

    Correct Option: D

    Let the work be finished in x days.
    According to the question, A worked for x days while B worked for (x – 3) days

    x
    +
    x - 3
    = 1
    1812

    2x + 3x - 9
    = 1
    36

    ⇒ 5x – 9 = 36
    ↠ 5x = 45
    ⇒ x =
    45
    = 9
    5

    Hence, the work was completed in 9 days.
    Aliter :
    Using Rule 8,
    Here, x = 18, y = 12, m = 3
    Total time taken =
    y + m
    x
    x + y

    =
    12 + 3
    × 18 = 9 days
    18 + 12


  1. 40 men can complete a work in 40 days. They started the work together. But at the end of each 10th day, 5 men left the job. The work would have been completed in









  1. View Hint View Answer Discuss in Forum

    For the first 10 days 40 men worked.
    Now, 40 men can complete the work in 40 days
    ∴ 1 man will complete the same work in 1600 days

    ∴ 1 man’s 1 day’s work
    1
    1600

    ∴ Part of work done in first 10 days
    =
    1
    4

    For the next 10 days 35 men worked.
    Part of the work done
    =
    1 × 35 × 10
    =
    7
    160016

    For the next 10 days, 30 men worked
    Part of the work done
    =
    30 × 10
    =
    3
    160016

    For the next 10 days, 25 men worked. Part of the work done
    =
    25 × 10
    =
    5
    160032

    Similarly, part of the work done by 20 men in next 10 days
    =
    20 × 10
    =
    1
    16008

    Work done in 50 days
    =
    1
    +
    7
    +
    3
    +
    5
    +
    1
    43216328

    =
    8 + 7 + 3 + 5 + 4
    =
    30
    =
    15
    323216

    ∴ Remaining work
    = 1 -
    15
    =
    1
    1616

    Now 15 men remain to work 15 men’s 1 day’s work
    =
    15
    1600

    ∴ Time taken to complete
    1
    part of work
    16

    =
    1600
    ×
    1
    1516

    =
    20
    = 6
    2
    days
    33

    ∴ Total time = 50 + 6
    2
    = 56
    2
    days
    33

    Correct Option: A

    For the first 10 days 40 men worked.
    Now, 40 men can complete the work in 40 days
    ∴ 1 man will complete the same work in 1600 days

    ∴ 1 man’s 1 day’s work
    1
    1600

    ∴ Part of work done in first 10 days
    =
    1
    4

    For the next 10 days 35 men worked.
    Part of the work done
    =
    1 × 35 × 10
    =
    7
    160016

    For the next 10 days, 30 men worked
    Part of the work done
    =
    30 × 10
    =
    3
    160016

    For the next 10 days, 25 men worked. Part of the work done
    =
    25 × 10
    =
    5
    160032

    Similarly, part of the work done by 20 men in next 10 days
    =
    20 × 10
    =
    1
    16008

    Work done in 50 days
    =
    1
    +
    7
    +
    3
    +
    5
    +
    1
    43216328

    =
    8 + 7 + 3 + 5 + 4
    =
    30
    =
    15
    323216

    ∴ Remaining work
    = 1 -
    15
    =
    1
    1616

    Now 15 men remain to work 15 men’s 1 day’s work
    =
    15
    1600

    ∴ Time taken to complete
    1
    part of work
    16

    =
    1600
    ×
    1
    1516

    =
    20
    = 6
    2
    days
    33

    ∴ Total time = 50 + 6
    2
    = 56
    2
    days
    33



  1. A can complete a piece of work in 10 days, B in 15 days and C in 20 days. A and C worked together for two days and then A was replaced by B. In how many days, altogether, was the work completed ?









  1. View Hint View Answer Discuss in Forum

    Work done by (A + C) in 2 days

    = 2
    1
    +
    1
    1020

    = 2
    2 + 1
    =
    6
    =
    3
    202010

    Remaining work = 1 -
    3
    =
    7
    1010

    (B + C)’s 1 day’s work
    =
    1
    +
    1
    =
    4 + 3
    =
    7
    15206060

    ∴ Time taken by (B + C) to finish
    7
    part of the work
    10

    =
    60
    ×
    7
    = 6 days
    710

    ∴ Total time = 2 + 6 = 8 days

    Correct Option: D

    Work done by (A + C) in 2 days

    = 2
    1
    +
    1
    1020

    = 2
    2 + 1
    =
    6
    =
    3
    202010

    Remaining work = 1 -
    3
    =
    7
    1010

    (B + C)’s 1 day’s work
    =
    1
    +
    1
    =
    4 + 3
    =
    7
    15206060

    ∴ Time taken by (B + C) to finish
    7
    part of the work
    10

    =
    60
    ×
    7
    = 6 days
    710

    ∴ Total time = 2 + 6 = 8 days


  1. A, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work before 5 days of its completion. B also left the work 2 days after A left. In how many days was the work completed?









  1. View Hint View Answer Discuss in Forum

    Let the work be completed in x days.
    According to the question

    x - 5
    +
    x - 3
    +
    x
    = 1
    101215

    6x - 30 + 5x - 15 + 4x
    = 1
    60

    ⇒ 15x – 45 = 60
    ⇒ 15x = 105 ⇒ x =
    105
    = 7
    15

    Hence, the work will be completed in 7 days.

    Correct Option: C

    Let the work be completed in x days.
    According to the question

    x - 5
    +
    x - 3
    +
    x
    = 1
    101215

    6x - 30 + 5x - 15 + 4x
    = 1
    60

    ⇒ 15x – 45 = 60
    ⇒ 15x = 105 ⇒ x =
    105
    = 7
    15

    Hence, the work will be completed in 7 days.



  1. A and B can complete a piece of work in 12 and 18 days respectively. A begins to do the work and they work alternatively one at a time for one day each. The whole work will be completed in









  1. View Hint View Answer Discuss in Forum

    A’s 1 day’s work =
    1
    12

    B’s 1 day’s work =
    1
    18

    Part of work done by A and B in first two days
    =
    1
    +
    1
    =
    3 + 2
    =
    5
    12183636

    Part of work done by A and B in 14 days
    =
    35
    36

    [14 days to be taken randomly]
    Remaining work = 1 -
    35
    =
    1
    3636

    Now A will work for 15th day
    A will do the
    1
    work in
    1
    × 12
    3636

    =
    1
    day
    3

    ∴ Total Work will be done in
    14
    1
    day.
    3

    Correct Option: A

    A’s 1 day’s work =
    1
    12

    B’s 1 day’s work =
    1
    18

    Part of work done by A and B in first two days
    =
    1
    +
    1
    =
    3 + 2
    =
    5
    12183636

    Part of work done by A and B in 14 days
    =
    35
    36

    [14 days to be taken randomly]
    Remaining work = 1 -
    35
    =
    1
    3636

    Now A will work for 15th day
    A will do the
    1
    work in
    1
    × 12
    3636

    =
    1
    day
    3

    ∴ Total Work will be done in
    14
    1
    day.
    3