Time and Work


  1. Raja can do a piece of work in 20 days while Ramesh can finish it in 25 days. Ramesh started working and Raja joined him after 10 days. The whole work is completed in









  1. View Hint View Answer Discuss in Forum

    Work done by Raja and Ramesh in 1 day

    =
    1
    +
    1
    =
    5 + 4
    =
    9
    2025100100

    Work done by Ramesh in 10 days
    =
    10
    =
    2
    255

    Remaining work = 1 –
    2
    =
    3
    55

    ∴ This part is done by Raja and Ramesh.
    ∴ Time taken
    =
    3
    ×
    100
    =
    20
    = 6
    2
    days.
    5933

    ∴ Required time
    = 10 + 6
    2
    = 16
    2
    days
    33

    Correct Option: B

    Work done by Raja and Ramesh in 1 day

    =
    1
    +
    1
    =
    5 + 4
    =
    9
    2025100100

    Work done by Ramesh in 10 days
    =
    10
    =
    2
    255

    Remaining work = 1 –
    2
    =
    3
    55

    ∴ This part is done by Raja and Ramesh.
    ∴ Time taken
    =
    3
    ×
    100
    =
    20
    = 6
    2
    days.
    5933

    ∴ Required time
    = 10 + 6
    2
    = 16
    2
    days
    33


  1. A, B and C can do a piece of work in 24, 30 and 40 days respectively. They began the work together but C left 4 days before completion of the work. In how many days was the work done ?









  1. View Hint View Answer Discuss in Forum

    Let the work be completed in x days.
    According to the question,
    C worked for (x – 4) days

    x
    +
    x
    +
    x - 4
    = 1
    243040

    5x + 4x + 3(x - 4)
    = 1
    120

    12x - 12
    = 1
    120

    12 (x - 1)
    = 1
    120

    x - 1
    = 1 ⇒ x - 1 = 10
    10

    ⇒ x = 10 + 1 = 11 days

    Correct Option: D

    Let the work be completed in x days.
    According to the question,
    C worked for (x – 4) days

    x
    +
    x
    +
    x - 4
    = 1
    243040

    5x + 4x + 3(x - 4)
    = 1
    120

    12x - 12
    = 1
    120

    12 (x - 1)
    = 1
    120

    x - 1
    = 1 ⇒ x - 1 = 10
    10

    ⇒ x = 10 + 1 = 11 days



  1. 20 men can do a piece of work in 18 days, They worked together for 3 days, then 5 men joined them. In how many more days is the work completed ?









  1. View Hint View Answer Discuss in Forum

    Work done by 20 men in 3 days

    =
    3
    =
    1
    part
    186

    Remaining work
    = 1 –
    1
    =
    5
    part
    66

    M1D1
    =
    M2D2
    W1W2

    20 × 18
    =
    25 × D2
    15/6

    ⇒ 6 × 25 × D2 = 5 × 20 × 18
    ⇒ D2 =
    5 × 20 × 18
    = 12 days
    6 × 25

    Aliter : Using Rule 10,
    Here, A = 20, a = 18 b = 3. B = 5
    Required number of days
    =
    A(a - b)
    =
    20 (18 - 3)
    A + B20 + 5

    =
    20 × 15
    = 12 days
    25

    Correct Option: B

    Work done by 20 men in 3 days

    =
    3
    =
    1
    part
    186

    Remaining work
    = 1 –
    1
    =
    5
    part
    66

    M1D1
    =
    M2D2
    W1W2

    20 × 18
    =
    25 × D2
    15/6

    ⇒ 6 × 25 × D2 = 5 × 20 × 18
    ⇒ D2 =
    5 × 20 × 18
    = 12 days
    6 × 25

    Aliter : Using Rule 10,
    Here, A = 20, a = 18 b = 3. B = 5
    Required number of days
    =
    A(a - b)
    =
    20 (18 - 3)
    A + B20 + 5

    =
    20 × 15
    = 12 days
    25


  1. A and B can do a piece of work in 45 and 40 days repectively. They began the work together but A left after some days and B finished the remaining work in 23 days. A left after









  1. View Hint View Answer Discuss in Forum

    Let A left the work after x days.
    According to the question,
    Work done by A in x days + work done by B in (23 + x ) days = 1

    x
    +
    23 + x
    = 1
    4540

    8x + 207 + 9x
    = 1
    360

    ⇒ 17x + 207 = 360
    ⇒ 17x = 360 – 207 = 153
    ⇒ x =
    153
    = 9 days
    17

    Aliter : Using Rule 26,
    Here, x = 45, y = 40, a = 23
    A left after =
    (y - a)
    × x
    x + y

    =
    (40 - 23)
    × 45
    45 + 40

    =
    17 × 45
    = 9 days
    85

    Correct Option: B

    Let A left the work after x days.
    According to the question,
    Work done by A in x days + work done by B in (23 + x ) days = 1

    x
    +
    23 + x
    = 1
    4540

    8x + 207 + 9x
    = 1
    360

    ⇒ 17x + 207 = 360
    ⇒ 17x = 360 – 207 = 153
    ⇒ x =
    153
    = 9 days
    17

    Aliter : Using Rule 26,
    Here, x = 45, y = 40, a = 23
    A left after =
    (y - a)
    × x
    x + y

    =
    (40 - 23)
    × 45
    45 + 40

    =
    17 × 45
    = 9 days
    85



  1. A certain number of men can do a piece of work in 40 days. If there were 45 men more the work could have been finished in 25 days. Find the original number of men employed in the work.









  1. View Hint View Answer Discuss in Forum

    Original number of men = x (let)
    ∴ M1 D1 = M2 D2
    ⇒ x × 40 = (x + 45) × 25
    ⇒ 8x = (x + 45) × 5
    ⇒ 8x = 5x + 225
    ⇒ 8x – 5x = 225
    ⇒ 3x = 225

    ⇒ x =
    225
    = 75 men
    3

    Aliter : Using Rule 23,
    Here, D = 40, a = 45, d = (40 – 25) = 15
    ∴ Required number=
    a(D - d)
    d

    =
    45(40 - 15)
    15

    =
    45 × 25
    = 15 × 5 = 75
    15

    Correct Option: D

    Original number of men = x (let)
    ∴ M1 D1 = M2 D2
    ⇒ x × 40 = (x + 45) × 25
    ⇒ 8x = (x + 45) × 5
    ⇒ 8x = 5x + 225
    ⇒ 8x – 5x = 225
    ⇒ 3x = 225

    ⇒ x =
    225
    = 75 men
    3

    Aliter : Using Rule 23,
    Here, D = 40, a = 45, d = (40 – 25) = 15
    ∴ Required number=
    a(D - d)
    d

    =
    45(40 - 15)
    15

    =
    45 × 25
    = 15 × 5 = 75
    15