Home » Aptitude » Time and Work » Question
  1. A can complete a piece of work in 10 days, B in 15 days and C in 20 days. A and C worked together for two days and then A was replaced by B. In how many days, altogether, was the work completed ?
    1. 12 days
    2. 10 days
    3. 6 days
    4. 8 days
Correct Option: D

Work done by (A + C) in 2 days

= 2
1
+
1
1020

= 2
2 + 1
=
6
=
3
202010

Remaining work = 1 -
3
=
7
1010

(B + C)’s 1 day’s work
=
1
+
1
=
4 + 3
=
7
15206060

∴ Time taken by (B + C) to finish
7
part of the work
10

=
60
×
7
= 6 days
710

∴ Total time = 2 + 6 = 8 days