  1. A can do a piece of work in 18 days and B in 12 days. They began the work together, but B left the work 3 days before its completion. In how many days, in all, was the work completed?
    1. 12 days
    2. 10 days
    3. 9.6 days
    4. 9 days
Correct Option: D

Let the work be finished in x days.
According to the question, A worked for x days while B worked for (x – 3) days

x
+
x - 3
= 1
1812

2x + 3x - 9
= 1
36

⇒ 5x – 9 = 36
↠ 5x = 45
⇒ x =
45
= 9
5

Hence, the work was completed in 9 days.
Aliter :
Using Rule 8,
Here, x = 18, y = 12, m = 3
Total time taken =
y + m
x
x + y

=
12 + 3
× 18 = 9 days
18 + 12