Time and Work


  1. 150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped on the second day, four more workers dropped on third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed?









  1. View Hint View Answer Discuss in Forum

    Let 150 workers complete the work in x days.
    ∴ 150 × x = 150 + 146 + .... to
    (x + 8) terms
    On putting x = 17
    LHS = 150 × 17 = 2550
    RHS = 150 + 146 + .... to 25 terms
    a = 150, d = –4, n = 25

    ∴ S =
    n
    [2a + (n–1) d]
    2

    =
    25
    [2 × 150 + 24 × (–4)]
    2

    =
    25
    (300 – 96) =
    25 × 204
    = 2550
    22

    Note : It is better to solve by options.

    Correct Option: C

    Let 150 workers complete the work in x days.
    ∴ 150 × x = 150 + 146 + .... to
    (x + 8) terms
    On putting x = 17
    LHS = 150 × 17 = 2550
    RHS = 150 + 146 + .... to 25 terms
    a = 150, d = –4, n = 25

    ∴ S =
    n
    [2a + (n–1) d]
    2

    =
    25
    [2 × 150 + 24 × (–4)]
    2

    =
    25
    (300 – 96) =
    25 × 204
    = 2550
    22

    Note : It is better to solve by options.


  1. 12 men and 18 boys working
    7
    1
    2

    hours a day can do a work in 60 days. If one man works equal to 2 boys, then the number of boys required to help 21 men to do twice the work in 50 days working 9 hours a day will be :









  1. View Hint View Answer Discuss in Forum

    Using Rule 1,
    12 men + 18 boys = 21 men

    ⇒ 9 × 50 × x =
    15
    × 60 × 21 × 2
    2

    ⇒ x =
    15 × 60 × 21 × 2
    = 42
    2 × 9 × 50 ×

    ∴ Number of boys
    = 2 × 21 = 42

    Correct Option: A

    Using Rule 1,
    12 men + 18 boys = 21 men

    ⇒ 9 × 50 × x =
    15
    × 60 × 21 × 2
    2

    ⇒ x =
    15 × 60 × 21 × 2
    = 42
    2 × 9 × 50 ×

    ∴ Number of boys
    = 2 × 21 = 42



  1. 8 workers can build a wall 18 m long, 2 m broad and 12 m high in 10 days, working 9 hours a day. Find how many workers will be able to build a wall 32 m long, 3 m broad and 9 m high in 8 days working 6 hours a day ?









  1. View Hint View Answer Discuss in Forum

    Using Rule 1,

    ⇒ 18 × 2 × 12 × 6 × 8x = 32 × 3 × 9 × 9 × 10 × 8

    ⇒ x =
    32 × 3 × 9 × 9 × 10 × 8
    = 30 days
    18 × 2 × 12 × 6 × 8

    Correct Option: C

    Using Rule 1,

    ⇒ 18 × 2 × 12 × 6 × 8x = 32 × 3 × 9 × 9 × 10 × 8

    ⇒ x =
    32 × 3 × 9 × 9 × 10 × 8
    = 30 days
    18 × 2 × 12 × 6 × 8


  1. If 12 carpenters working 6 hours a day can make 460 chairs in 240 days, then the number of chairs made by 18 carpenters in 36 days each working 8 hours a day is









  1. View Hint View Answer Discuss in Forum

    Using Rule 1,

    ⇒ 12 × 6 × 240 × x
    ⇒ = 18 × 8 × 36 × 460

    ⇒ x =
    18 × 8 × 36 × 460
    = 138
    12 × 6 × 240

    Correct Option: C

    Using Rule 1,

    ⇒ 12 × 6 × 240 × x
    ⇒ = 18 × 8 × 36 × 460

    ⇒ x =
    18 × 8 × 36 × 460
    = 138
    12 × 6 × 240



  1. A farmer can plough a field working 6 hours per day in 18 days. The worker has to work how many hours per day to finish the same work in 12 days ?









  1. View Hint View Answer Discuss in Forum

    Using Rule 1,
    D1T1 = D2T2
    ⇒ 18 × 6 = 12 × T2

    ⇒ T2 =
    18 × 6
    = 9 hours
    12

    Correct Option: B

    Using Rule 1,
    D1T1 = D2T2
    ⇒ 18 × 6 = 12 × T2

    ⇒ T2 =
    18 × 6
    = 9 hours
    12