Time and Work
- If 10 men can do a piece of work in 12 days, the time taken by 12 men to do the same piece of work will be
-
View Hint View Answer Discuss in Forum
Where = number of days
⇒ 12 : 10 :: 12 : x
⇒ 12 × x = 10 × 12⇒x = 10 × 12 = 10 days 12
Aliter : Using Rule 1,
Here, M1 = 10, D1 = 12
M2 = 12, D2 = ?
M1D1 = M2D2
10 × 12 = 12 × D2
D2 = 10 daysCorrect Option: B
Where = number of days
⇒ 12 : 10 :: 12 : x
⇒ 12 × x = 10 × 12⇒x = 10 × 12 = 10 days 12
Aliter : Using Rule 1,
Here, M1 = 10, D1 = 12
M2 = 12, D2 = ?
M1D1 = M2D2
10 × 12 = 12 × D2
D2 = 10 days
- 7 men can complete a piece of work in 12 days. How many additional men will be required to complete double the work in 8 days ?
-
View Hint View Answer Discuss in Forum
∴ 1 : 2 : : 7 : x 8 : 12
where, x is no. of men
⇒ 1 × 8 × x = 2 × 12 × 7⇒ x = 2 × 12 × 7 = 21 8
∴ Number of additional men
= 21 – 7 = 14
Metod 2 :
Using Rule 1,
M1D1W2 = M2D2W1
⇒ 7 × 12 × 2 = M2 × 8 × 1⇒ M2 = 7 × 12 × 2 = 21 8
∴ No. of additional men
= 21 – 7 = 14Correct Option: C
∴ 1 : 2 : : 7 : x 8 : 12
where, x is no. of men
⇒ 1 × 8 × x = 2 × 12 × 7⇒ x = 2 × 12 × 7 = 21 8
∴ Number of additional men
= 21 – 7 = 14
Metod 2 :
Using Rule 1,
M1D1W2 = M2D2W1
⇒ 7 × 12 × 2 = M2 × 8 × 1⇒ M2 = 7 × 12 × 2 = 21 8
∴ No. of additional men
= 21 – 7 = 14
- ‘x’ number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men is
-
View Hint View Answer Discuss in Forum
x + 6 : x : : 30 : 20⇒ x + 6 = 30 = 3 x 20 2
⇒ 2x + 12 = 3x
⇒ 3x – 2x = 12
⇒ x = 12
Aliter : Using Rule 1,
Here, M1 = x, D1 = 30
M2 = x + 6, D2 = 20
M1D1 = M2D2
x × 30 = (x + 6) × 20
3x = 2 x + 12
x = 12Correct Option: C
x + 6 : x : : 30 : 20⇒ x + 6 = 30 = 3 x 20 2
⇒ 2x + 12 = 3x
⇒ 3x – 2x = 12
⇒ x = 12
Aliter : Using Rule 1,
Here, M1 = x, D1 = 30
M2 = x + 6, D2 = 20
M1D1 = M2D2
x × 30 = (x + 6) × 20
3x = 2 x + 12
x = 12
- Some carpenters promised to do a job in 9 days but 5 of them were absent and remaining men did the job in 12 days. The original number of carpenters was
-
View Hint View Answer Discuss in Forum
Using Rule 1,
Let the original number of carpenters be x.
M1D1 = M2D2
⇒ x × 9 = (x – 5) × 12
⇒ 9x = 12x – 60
⇒ 3x = 60 ⇒ x = 20Correct Option: B
Using Rule 1,
Let the original number of carpenters be x.
M1D1 = M2D2
⇒ x × 9 = (x – 5) × 12
⇒ 9x = 12x – 60
⇒ 3x = 60 ⇒ x = 20
- 2 men and 3 women together or 4 men together can complete a piece of work in 20 days.3 men and 3 women will complete the same work in :
-
View Hint View Answer Discuss in Forum
Using Rule 1,
2 men + 3 women ≡ 4 men
⇒ 2 men ≡ 3 women
∴ 3 men + 3 women ≡ 5 men
∴ M1D1 = M2D2
⇒ 4 × 20 = 5 × D2⇒ D2 = 4 × 20 = 16 days 5 Correct Option: B
Using Rule 1,
2 men + 3 women ≡ 4 men
⇒ 2 men ≡ 3 women
∴ 3 men + 3 women ≡ 5 men
∴ M1D1 = M2D2
⇒ 4 × 20 = 5 × D2⇒ D2 = 4 × 20 = 16 days 5