Home » Aptitude » Time and Work » Question
  1. A and B alone can complete work in 9 days and18 days respectively. They worked together; however 3 days before the completion of the work A left. In how many days was the work completed ?
    1. 13 days
    2. 8 days
    3. 6 days
    4. 5 days
Correct Option: B

Let the work be completed in x days.
According to the question,
A worked for (x –3) days, while B worked for x days.

x - 3
+
x
= 1
918

2x - 6 + x
= 1 ⇒ 3x - 6 = 18
18

⇒ 3x = 18 + 6 = 24
∵ x =
24
= 8 days
3

Aliter :
Using Rule 8,
Here, x = 9, y = 18, m = 3
Total time taken =
(x + m)y
x + y

=
(9 + 3) × 18
9 + 18

=
12 × 18
= 8 days