  1. A can do a piece of work in 120 days and B can do it in 150 days. They work together for 20 days. Then B leaves and A alone continues the work. 12 days after that C joins A and the work is completed in 48 days more. In how many days can C do it if he works alone?
    1. 230 days
    2. 225 days
    3. 240 days
    4. 220 days
Correct Option: C

A’s 1 day’s work

=
1
120

B’s 1 day’s work =
1
150

(A + B)’s 1 day’s work
=
1
+
1
=
5 + 4
=
3
120150600200

(A + B) work together for 20 days
Hence, (A + B)’s 20 days’ work
= 20 ×
3
=
3
20010

After 20 days B leaves, and A alone works for 12 days
∴ A’s 12 days’ work
=
1
× 12=
2
12010

Now, after 12 days, C joins A and the work is finished in 48 days. It means A works for 48 days more.
∴ A’s 48 days’ work
=
1
× 48 =
2
1205

∴ Total work done by A and B together
=
3
+
1
+
2
10105

=
3 + 1 + 4
=
4
105

∴ Remaining work
= 1 -
4
=
1
55

This part of work, i.e., 1/5 is done by C in 48 days
∴ C’s 48 days’ work =
1
5

∴ C’s 1 day’s work
=
1
=
1
5 × 48240

Hence, C alone can finish the work in 240 days.