-
A can do a piece of work in 120 days and B can do it in 150 days. They work together for 20 days. Then B leaves and A alone continues the work. 12 days after that C joins A and the work is completed in 48 days more. In how many days can C do it if he works alone?
-
- 230 days
- 225 days
- 240 days
- 220 days
Correct Option: C
A’s 1 day’s work
= | 120 |
B’s 1 day’s work = | 150 |
(A + B)’s 1 day’s work
= | + | = | = | |||||
120 | 150 | 600 | 200 |
(A + B) work together for 20 days
Hence, (A + B)’s 20 days’ work
= 20 × | = | |||
200 | 10 |
After 20 days B leaves, and A alone works for 12 days
∴ A’s 12 days’ work
= | × 12= | |||
120 | 10 |
Now, after 12 days, C joins A and the work is finished in 48 days. It means A works for 48 days more.
∴ A’s 48 days’ work
= | × 48 = | |||
120 | 5 |
∴ Total work done by A and B together
= | + | + | ||||
10 | 10 | 5 |
= | = | |||
10 | 5 |
∴ Remaining work
= 1 - | = | |||
5 | 5 |
This part of work, i.e., 1/5 is done by C in 48 days
∴ C’s 48 days’ work = | 5 |
∴ C’s 1 day’s work
= | = | |||
5 × 48 | 240 |
Hence, C alone can finish the work in 240 days.