  1. A can complete a work in ‘m’ days and B can complete it in ‘n’ days. How many days will it take to complete the work if both A and B work together ?
    1. ( m + n ) days
    2. 1
      ×
      1
      days
      mn
    3. m + n
      days
      mn
    4. mn
      days
      m + n
Correct Option: D

A’s 1 day’s work =
1
m

B’s 1 day’s work =
1
n

∴ (A + B)’s 1 day’s work =
1
+
1
mn

(A + B)’s 1 day’s work =
m + n
=
m + n
mnmn

∴ Required time =
mn
m + n