A can do a piece of work in 70 days and B is 40% more efficient than A. The number of days taken by B to do the same work is
-
- 40 days
- 60 days
- 50 days
- 45 days
Correct Option: C
A : B = D2 : D2
⇒ 100 : 140 = D2 : 70
⇒ 100 × 70 = 140 × D2
⇒ D2 = | = 50 days. | 140 |
Aliter : Using Rule 17,
Here, x = 70, r = 40%
Time taken by B
= x × | 100 + R |
= | = 50 days | 100 + 40 |