  1. A can do a piece of work in 70 days and B is 40% more efficient than A. The number of days taken by B to do the same work is
    1. 40 days
    2. 60 days
    3. 50 days
    4. 45 days
Correct Option: C

A : B = D2 : D2
⇒ 100 : 140 = D2 : 70
⇒ 100 × 70 = 140 × D2

⇒ D2 =
100 × 70
= 50 days.
140

Aliter : Using Rule 17,
Here, x = 70, r = 40%
Time taken by B
= x ×
100
100 + R

=
70 × 100
= 50 days
100 + 40