  1. A man does double the work done by a boy in the same time. The number of days that 3 men and 4 boys will take to finish a work which can be done by 10 men in 8 days is
    1. 4
    2. 16
    3. 7
      3
      11
    4. 8
      4
      days
      5
Correct Option: B

According to the question,
1 man ≡ 2 boys
∴ 3 men + 4 boys ≡ (3 + 2) men ≡ 5 men
∴ M1D1 = M2D2
⇒ 5 × D1 = 10 × 8

⇒ D1 =
10 × 8
= 16 days
5