A and B can do a piece of work in 18 days, B and C in 24 days, A and C in 36 days. Working together they can do the work in
-
- 12 days
- 13 days
- 16 days
- 26 days
Correct Option: C
(A + B)’s 1 day’s work = | 18 |
(B + C)’s 1 day’s work = | 24 |
(C + A)’s 1 day’s work = | 36 |
On adding all three,
2 (A + B + C)’s 1 day’s work
= | + | + | = | |||||
18 | 24 | 36 | 72 |
= | = | |||
72 | 8 |
∴ (A + B + C)’s 1 day’s work
= | 16 |
∴ Required time = 16 days