Home » Aptitude » Time and Work » Question
  1. A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?
    1. 100
    2. 60
    3. 75
    4. None of these
Correct Option: C

Scheduled time to complete the work = 40 days

25 men in 24 days do
1
work
3

∴ 1 man in 1 day does
1
=
1
work.
3 × 25 × 241800

Work remaining
= 1 -
1
=
2
33

The work is to be completed 4 days before schedule i.e., in (40 – 4) 36 days
No. of days left for
2
rd work
3

= 36 – 24 = 12 days
1
1800

work is done in 1 day by 1 man.
2
work will be done in 12 days by
3

1800 ×
2
×
1
= 100 men
312

25 men are already working
∴ Extra men to be employed
= 100 – 25 = 75



Your comments will be displayed only after manual approval.