  1. A can do 1/2 of a piece of work in 5 days, B can do 3/5 of the same work in 9 days and C can do 2/3 of that work in 8 days. In how many days can three of them together do the work ?
    1. 3 days
    2. 5 days
    3. 4
      1
      days
      2
    4. 4 days
Correct Option: D

Using basics of Rule 3,

A can do
1
work in 5 days.
2

∴ A can do 1 work in 10 days
Similarly,
B can do 1 work in
5
× 9 = 15 days
3

C can do 1 work in 8 ×
3
= 12 days.
2

Now,
A’s 1 day’s work =
1
10

B’s 1 day’s work =
1
15

C’s 1 day’s work =
1
12

∴ (A + B + C)’s 1 day’s work
=
1
+
1
+
1
101512

=
6 + 4 + 5
=
15
=
1
60604

Hence, (A + B + C) together can complete the work in 4 days.