  1. A can complete a work in 6 days while B can complete the same work in 12 days. If they work together and complete it, the portion of the work done by A is
    1. 1
      3
    2. 2
      3
    3. 1
      4
    4. 1
      2
Correct Option: B

Using basics of Rule 2,
Time taken by A and B

=
6 × 12
=
6 × 12
= 4
6 + 1218

∴ Work done by A in 4 days
=
4
=
2
63