Home » Aptitude » Time and Work » Question
  1. A can complete 2/3 of a work in 4 days and B can complete 3/5 of the work in 6 days. In how many days can both A and B together complete the work ?
    1. 3
    2. 2
    3. 3
      3
      4
    4. 2
      7
      8
Correct Option: C

Using basics of Rule 2,
Time taken by A to complete the work

=
4 × 3
= 6 days
2

Time taken by B to complete the work
=
6 × 5
= 10 days
3

∴ (A + B)’s 1 day’s work
=
1
+
1
=
5 + 3
=
4
6103015

∴ A and B together will complete the work in
15
= 3
3
days.