  1. A contractor undertook to complete a project in 90 days and employed 60 men on it. After 60 days, he found that 3/4 of the work has already been completed. How many men can he discharge so that the project may be completed exactly on time ?
    1. 40
    2. 20
    3. 30
    4. 15
Correct Option: B

Using basics of Rule 1,

⇒ 30 ×
3
× x = 60 ×
1
× 60
44

⇒ x =
60 × 60
= 40
30 × 3

∴ 20 men should be discharged.