  1. 8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?
    1. 2
    2. 3
    3. 4
    4. 5
Correct Option: C

Using Rule 1,
Work done by 8 men in 6 days

=
6
=
1
122

Remaining work = 1 -
1
=
1
22

4 more men are engaged.
∴ Total number of men
= 8 + 4 = 12
By work and time formula
W1
=
W2
, we have
M1D1M2D2

1
=
1/2
8 × 1212 × D2

⇒ D2 =
1
×
8 × 12
= 4 days
212