8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?
-
- 2
- 3
- 4
- 5
Correct Option: C
Using Rule 1,
Work done by 8 men in 6 days
| = | = | |||
| 12 | 2 |
| Remaining work = 1 - | = | |||
| 2 | 2 |
4 more men are engaged.
∴ Total number of men
= 8 + 4 = 12
By work and time formula
| = | , we have | |||
| M1D1 | M2D2 |
| = | ||||
| 8 × 12 | 12 × D2 |
| ⇒ D2 = | × | = 4 days | ||
| 2 | 12 |