A and B can do a piece of work in 30 days while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work ?
-
- 18 days
- 24 days
- 30 days
- 36 days
Correct Option: A
(A + B)’s day’s work = | 30 |
(B + C)’s 1 day’s work = | 24 |
(C + A)’s 1 day’s work = | 20 |
∴ 2 (A + B + C)’s 1 day’s work
= | + | + | ||||
30 | 24 | 20 |
= | = | = | ||||
120 | 120 | 8 |
∴ (A + B + C)’s 1 day’s work
= | 16 |
∴ (A + B + C)’s 10 days’ work
= | = | |||
16 | 8 |
∴ Remaining work = 1 - | = | |||
8 | 8 |
This part of work is done by A alone.
Now A’s 1 day’s work = | - | |||
16 | 24 |
= | = | |||
48 | 48 |
∴ The required no. of days
= | × 48 = 18 days | 8 |