Home » Aptitude » Time and Work » Question
  1. A and B can do a job in 6 and 12 days respectively. They began the work together but A leaves after 3 days. Then the total number of days needed for the completion of the work is :
    1. 4 days
    2. 5 days
    3. 6 days
    4. 9 days
Correct Option: C

A’s one day’s work =
1
6

B’s one day’s work =
1
12

(A + B)’s one day’s work
=
1
+
1
=
2 + 1
=
1
612124

table>(A + B)’s three day’s work =
3
4
Remaining work = 1 -
3
=
1
44

∴ Total required number of days
=
1
×
12
+ 3 = 3 + 3 = 6 days
41

Aliter : Using Rule 20,
Here, m = 6, n= 12, and p = 3
Time taken by B
=
mn - (m + n)p
m

=
6 × 12 - (6 + 12) × 3
6

=
72 - 54
= 3 days
6

∴ Total number of days taken to finish the works = 6 days